HomeMy WebLinkAboutCity of Tamarac Resolution R-2018-091Temp. Reso. #13141 August 22, 2018 Page 1 of 5 CITY OF TAMARAC, FLORIDA / RESOLUTION NO. R-2018- ! / A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF TAMARAC, FLORIDA, APPROVING TASK AUTHORIZATION NO. 18-19D AND AUTHORIZING THE APPROPRIATE CITY OFFICIALS TO EXECUTE TASK AUTHORIZATION NO. 18-19D WITH ECKLER ENGINEERING, INC., TO PROVIDE PROFESSIONAL SERVICES FOR THE DESIGN OF THE LIFT STATIONS 16A, 34, 37 AND 2E GENERATOR ADDITION PROJECT IN THE AMOUNT NOT TO EXCEED $102,823.00; INCLUDING PREPARATION OF DETAILED PLANS AND SPECIFICATIONS FOLLOWED BY BIDDING ASSISTANCE AND ENGINEERING SERVICES DURING CONSTRUCTION, IN ACCORDANCE WITH THE CITY'S CONSULTING ENGINEERING AGREEMENT AS AUTHORIZED BY RESOLUTION NO. R-2016-80, FOR AN AMOUNT NOT TO EXCEED $102,823.00; AUTHORIZING AN APPROPRIATION UP TO THE TOTAL AMOUNT OF $102,823; AUTHORIZING THE APPROPRIATE CITY OFFICIALS TO ADMINISTER THE CONTRACT; PROVIDING FOR CONFLICTS; PROVIDING FOR SEVERABILITY; AND PROVIDING FOR AN EFFECTIVE DATE. WHEREAS, the City of Tamarac owns, operates and maintains eighty-six (86) lift stations throughout the City; and WHEREAS, it is necessary to provide proper and adequate electrical power to the City of Tamarac's eighty-six (86) lift stations; and WHEREAS, the City of Tamarac identified several lift stations throughout the City of Tamarac where there were problems caused by power outages during previous Temp. Reso. #13141 August 22, 2018 Page 2 of 5 hurricanes and heavy rain events; and WHEREAS, Lift Station (LS) 16A services Millennium and Challenger schools, which are both used as hurricane shelters. LS 34 and LS 37 services high volume residential areas and LS 2E, which is the furthest station from the Public Services grounds, and the most difficult to get to during or immediately after hurricanes or heavy rain events; and WHEREAS, this project will provide Professional Engineering Services for the Design and Construction Administration phases for four (4) new Generator Additions at Lift Stations 16A, 34, 37 and 2E in the amount of $102,823.00, and WHEREAS, Task Authorization No 18-19D with Eckler Engineering, Inc. will provide for a Design phase costing $57,150.00 which will include preparation of detailed plans and specifications and a Construction Administration Phase with a cost not -to - exceed an amount of $45,673.00; and WHEREAS, the City requires the service of a consulting firm knowledgeable in this area and capable of providing professional services for the design, permitting, bidding and Construction Administration for the design of four (4) new Generator Additions at Lift Stations 16A, 34, 37 and 2E in the amount of $102,823.00; and WHEREAS, Eckler Engineering, Inc. possesses the required knowledge and experience to provide the Professional Engineering Services associated with the Generator Additions at Lift Stations 16A, 34, 37 and 2E, and WHEREAS, Eckler Engineering, Inc. has been pre -qualified as an approved consultant for Engineering Services by the City of Tamarac as authorized by Resolution R-2016-80; and Temp. Reso. #13141 August 22, 2018 Page 3of5 WHEREAS, Task Authorization No. 18-19D is allowable pursuant to Florida Statute 287.055 under the City's Consultant Engineering Agreement since the estimated construction cost is less than $2,000,000.00; and WHEREAS, it is the recommendation of the Director of Public Services, Financial Services Director, and the Purchasing and Contracts Manager that Task Authorization No. 18-19D from Eckler Engineering, Inc. be approved and executed by the appropriate City Officials; and WHEREAS, the City Commission of the City of Tamarac, Florida, deems it to be in the best interest of the citizens and residents of the City of Tamarac to accept and execute Task Authorization No. 18-19D (attached as "Exhibit 1 ") with Eckler Engineering, Inc. to provide professional Engineering Services for the Design and Construction Administration of four (4) new Generator Additions at Lift Stations 16A, 34, 37 and 2E for a total amount not to exceed $102,823.00. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF TAMARAC, FLORIDA, THAT: SECTION 1: The foregoing "WHEREAS" clauses are hereby ratified and confirmed as being true and correct and are hereby made a specific part of this Resolution upon adoption hereof. All Exhibits attached hereto are incorporated herein and made a specific part hereof. SECTION 2: The City Commission approves Task Authorization No. 18- 19D and authorizes the appropriate City Officials to execute Task Authorization No. 18- 19D with Eckler Engineering, Inc., to provide Engineering Services for the design and bidding assistance along with Engineering Services during construction of the four (4) new Generator Additions at Lift Stations 16A, 34, 37 and 2E, in accordance with the City's Temp. Reso. #13141 August 22, 2018 Page 4 of 5 Consulting Engineering Agreement as authorized by Resolution No. R-2016-80 on August 24, 2016, for an amount not to exceed $102,823.00. SECTION 3: An appropriation of an amount up to $102,823 is hereby authorized and will be included in a budget amendment prior to November 30, 2018. SECTION 4: The City Manager, or his Designee, is hereby authorized to approve and initiate change orders not to exceed $65,000.00 per Section 6-147 of the City Code, and close the contract award including, but not limited to making final payment within the terms and conditions of the contract and within the contract price. SECTION 5: All Resolutions or parts of Resolutions in conflict herewith are hereby repealed to the extent of such conflict. SECTION 6: If any clause, section, other part or application of this Resolution is held by any court of competent jurisdiction to be unconstitutional or invalid, in part or application, it shall not affect the validity of the remaining portions or applications of this Resolution. Temp. Reso. #13141 August 22, 2018 Page 5of5 SECTION 7: This Resolution shall become effective immediately upon its passage and adoption. PASSED, ADOPTED AND APPROVED this day of &W16+ 2018. 4Rkk DRESSLER, MAYOR ATTEST: ATRICIA TEUFEL, C CITY CLERK RECORD OF COMMISSION VOTE: MAYOR DRESSLER DIST 1: COMM. BOLTON DIST 2: V/M GOMEZ DIST 3: COMM. FISHMAN DIST 4: COMM. PLACKO I HEREBY CERTIFY THAT I HAVE APPROVED THIS RESOLUTION AS TO FORM 4i$AEL S. GOREN CITY ATTORNEY "EXHIBIT 1" rEECKLER ENGINEERING, INC. May 16, 2018 442-000.BD Mr. Earl Henry, P.E., Utility Engineer City of Tamarac Public Services Department 10101 State Street Tamarac, FL 33321 Dear Mr. Henry: Reference: Proposal for Engineering Services Task Authorization No. 18-19D Lift Stations 16A, 34, 37, and 2E Generator Additions In accordance with your request, we are pleased to submit this proposal for providing engineering services for the proposed Lift Stations 16A, 34, 37, and 2E Generator Additions. The scope of services proposal includes: ► Preliminary and final design of the anticipated improvements described herein ► Preparation of drawings and specifications for the improvements. ► Limited Bidding Phase Assistance. P. Limited traditional and special engineering services during construction. The proposed scope of work for this project is attached as Task Authorization 18-19D. Our proposed lump sum fee for the design phase services required for this scope is $57,150.00. A breakdown of the design engineering fee calculation is attached at the end of the enclosed Task Authorization. Our proposed not -to -exceed estimate for engineering services required during the construction phase of this project is $45,673.00. A breakdown of the fee calculation is attached at the end of the enclosed task authorization. The engineering services for the construction phase will be billed on an hourly rate plus direct expenses basis in accordance with the attached breakdown. Any unused portion of the construction services fee will not be billed to the City. If this proposal meets with your approval, please provide us with one signed copy of the enclosed task authorization along with a City PO for this work. "Celebrating Service to South Florida Since 19W' 4700 RIVERSIDE DRIVE, SUITE 110 954,610-4700 CORAL SPRINGS, FL 33067 FAX 9541755-2741 Mr. Earl Henry, P.E. May 16, 2018 Page 2 Eckler Engineering looks forward to working with the City of Tamarac on this emergency power supply project. If you have any questions or require additional information pertaining to the enclosed scope of services or the project in general, please do not hesitate to contact me. Si cerely, Douglas K. Hammann, P.E. Encl. Y:\Documents\TamarackBD\Task Authorizartion 18-19D LS Generators\Task Authorization\Task Auth 18-19D.wpd TASK AUTHORIZATION NO. 18-19D SCOPE OF SERVICES LIFT STATIONS 16A, 34, 37, AND 2E GENERATOR ADDITIONS INTRODUCTION Eckler Engineering met with the City of Tamarac to discuss the emergency generator/power improvements planned for existing LS-16A, 34, 37, and 2E. The general scope of this project is preliminary and final design, preparation of drawings and specifications, permitting, bidding phase assistance, and engineering services during construction of this project. In accordance with our project meeting of April 19, 2018, the following design scope is recommended and included in this project proposal: Generator Addition at LS-16A, 34, 37, and 2E Work scope is anticipated to be similar at each site. New Emergency standby diesel engine generator set. Design will be based on an exterior located, reach -in style, as manufactured by Caterpillar. Package will include a base fuel storage tank sized for three (3) continuous days of operation based on current FPL demands. 2. New Automatic transfer switch (ATS) and main facility breaker. 3. New power feeder to new generator set load center. 4. Miscellaneous electrical distribution improvements to serve existing lift station from new generator. New raceways for proposed electrical improvements. 6. Minor demolition work to facilitate the proposed improvements. Design of general aesthetic and site work to be included at this site including but not limited to the following: ► Reinforced concrete foundation/slab for new generator. ► Addition of 6' or 8' chain link fencing of lift station site perimeter, where feasible. Feasibilityto be determined by OWNER and ENGINEER based on: site availability, setback requirements, deed restrictions, impact to other utilities, site triangles, etc. ► General site cleanup and restoration. ► Miscellaneous site work improvements inclusive of grading, sidewalks, pavement restoration and sodding, as applicable. 8. Design considerations/coordination for main and emergency power systems to allow uninterrupted service during completion of the work. Page 1 of 19 Automatic Transfer Switch Addition at LS-18 18B. 2A, and 7E. Work scope is anticipated to be similar at the sites. 1. New automatic transfer switch and main facility breaker. 2. New raceways for proposed electrical improvements. 3. Minor demolition work to facilitate proposed improvements. 4. Design of general aesthetics and sitework to be included at the sites including, but not limited to, the following: a. Reinforced concrete foundation/slab for new ATS. Slab shall also include foundation and support structure for mounting the new ATS. b. General site cleanup and restoration. 5. Design consideration/coordination for primary emergency power systems to allow uninterrupted service during completion of the work. The opinion of probable construction cost for the above listed improvements is in the range of $386,000 to $576,000 depending on specified generator manufacturer. The engineering tasks associated with this project are presented below: ARTICLE 1 - SCOPE OF SERVICES Design Phase Task D1- Project Administration/Management This task focuses on the administration of the project including project setup, client interface and general project management and administration. Task D2 - Data Evaluation and Preliminary Design This task focuses on obtaining the necessary preliminary information required to prepare detailed engineering plans and specifications. A. Meet with CITY project staff to discuss and confirm project requirements and design criteria. B. Visit the sites and review pertinent features that may impact design and/or construction. C. Collect data available for the existing facilities, including field conditions, record drawings, FPL service information, and other information that may potentially impact the project. Page 2 of 19 D. Coordinate scope and completion of work by the surveyor and electrical subconsultant. Task D3 - Preliminary Design Report (Memorandum) This task not required. Task D4 - Drawings and Engineering This task consists of the engineering and the development of plans necessary to construct this project. A. Prepare detailed drawings for the proposed work discussed previously within this Exhibit. A tentative list of final design drawings to be developed for this project is presented in Table 1. Drawings will be prepared using drafting standards and standard details as developed by Eckler Engineering, Inc. Task D5 - Specification Preparation This task consists of the preparation of specifications necessary to construct this project. A. ENGINEER shall prepare technical specifications required for this project. These specifications will be prepared and will consist of written technical descriptions and materials, equipment and construction systems, standards and workmanship required for this project as developed by Eckler Engineering. B. The City of Tamarac standard bidding requirements, contract forms and miscellaneous forms/information required for this project shall be utilized. Consultant shall provide the City of Tamarac with project specific information for the preparation of bidding and contract documents required for this project. C. A tentative list of specification sections to be prepared for this project is presented in Table 2, Task D6 - Permit Preparation Assistance This task consists of preparing the following regulatory permit application submittals for each site: A. None required during design phase. Any additional regulatory permits required beyond the above will be considered as outside the scope of this proposal. Building permits (where applicable) during construction are obtained by Contractor per the contract documents. Task D7 - Prepare Opinions of Probable Construction Cost Prepare the 90%, 100%, and final design levels of Opinion of Probable Construction Cost for new facilities and improvements proposed under this project. Page 3 of 19 Task D8 - Bidding Assistance Services This task shall include work necessary to assist CITY with the bidding of this project. This work may include the following: A. Assist with the coordination of the bidding documents and the advertisement for bid and respond to communication from contractors and issue addenda information as required. Provide bid documents (on CD) to be used by the CITY to upload files for electronic distribution to potential bidders. B. Attend the pre -bid meeting and assist City with preparation of and distribution of minutes. C. Respond to written questions by potential bidders and, if needed, assist the CITY in issuing addenda. Task D9 - Bid Evaluation and Recommendation of Award Assistance This task shall consist of the review and evaluation of the bids and the recommendation of a bidder for award of contract to the CITY. Task D10 - Submit and Review (Quality Control) The ENGINEER will make the following submittals at various completion levels of this project for the purpose of CITY's review and comment for coordination and quality control. A review meeting will be requested following each submittal to discuss and receive comments from CITY. The CITY's comments shall be incorporated into revisions prior to the next subsequent quality control submittal. Quality control submittals for this project are anticipated at the following completion levels: A. 90% Drawings and Specifications. B. 100% Drawings and Specifications. The ENGINEER will incorporate the agreed -upon revisions made by the CITY. A total of two (2) meetings with the CITY is the level of effort for this Task. Construction Phase Task C1 - Project Administration/Management This task focuses on the administration of the project including project setup, client interface and general project management and administration. Task C2 - Preconstruction Activities Prior to Notice to Proceed After issuance of a Notice of Award by City, ENGINEER shall: Page 4 of 19 A. Assist the City in the preparation and signing of the Contract Documents by reviewing insurance certificates and incorporation of Addendum information to develop a conformed set of Contract Documents. B. Distribution of documents to the City and Contractor. C. Presiding over the preconstruction meeting and providing preconstruction meeting minutes to all attendees. D. Assisting the Contractor in finalizing any permit application issues or technical assistance with any building permit review issues or questions required for the construction of this project and by providing the required number of signed/sealed drawing sets for building permits. E. Provide Contractor sets of Contract Documents required for construction. Task C3 - Consult and Advise Provide technical advise and assistance to City during the construction period and provide necessary interpretations and clarifications of the Contract Documents as required by City or Contractor. Review and respond to eight (8) Requests for Information (RFI) is the level of effort basis for this task. Task C4 - Review Shop Drawings Review Shop Drawings and samples, the results of tests and inspections, and other data submitted by the Contractor in accordance with the Contract Documents shall then be sent to the City for review and comment, appropriately marked and then returned to the Contractor. A total of twenty (20) submittals is the estimated level of effort basis for this item's budget. Task C5 - Review Pay Requests and Schedules Review monthly pay requests and make recommendations for payment to CITY. Monthly pay requests will be reviewed in the field and an agreement reached between the Contractor, CITY's project representative, and the ENGINEER prior to formal submittal to CITY for payment. Review the Contractor's preliminary and monthly progress schedules through completion. Task C6 - Perform Periodic and Milestone Inspections ENGINEER will make periodic site visits at intervals appropriate to the various stages of construction to observe the work, determine conformity with the contract documents and compliance with the construction permits. It is anticipated that there will be eight (8) site visits. Perform inspections to determine that the project has achieved Substantial Completion and readiness for Final Acceptance and that the Work has been completed in conformance with the Contract Documents to certify completion of construction to permitting agencies. Two (2) such site visits are anticipated. Task C7 - Progress Meetings This task not required. Page 5 of 19 Task C8 - Contract Modifications Develop the necessary data, notes and clarification drawings required to prepare contract modifications to reflect adjustments to the construction project. Three (3) contract modifications incorporating a total of six items, is the estimate basis for this budget item. One of the contract modifications will be the final reconciliation contract modification prepared at the end of the project. When CITY requests additional contract modifications, the ENGINEER's fee may be adjusted accordingly based on a mutually agreed amount. Task C9 - Project Closeout Review the Contractor's record drawing information which shows the work as it was constructed. Prepare for CITY sets of record drawings showing those changes made during the construction progress based upon information provided by the Contractor. A. ENGINEER shall prepare signed and sealed record drawings based on Contractor's field data. B. ENGINEER shall submit final copies of record drawings to CITY. C. ENGINEER shall provide record drawings to CONTRACTOR for building permit closeout submittal (electronic signature/submittal requirement). D. Attend the final project reconciliation meetings with CITY and the Contractor. Task C10 - Regulatory Agency Documentation and Project Closeout Submittals This task covers preparation of regulatory agency permit closeout documentation for each regulatory permit obtained for the project as follows: A. Broward County Environmental Protection and Growth Management Department (BCEP&GMD). Following tank installation(s), ENGINEER shall prepare submittal documentation for Hazardous Material Storage Facility License (under 600 gallons) to BCEP&GMD. B. City of Tamarac Building Department Task C11 - Special Services Shall be provided by the CITY. Task C12 - Special Inspection This task not required. ARTICLE 2 - DATA OR ASSISTANCE TO BE PROVIDED BY CITY A. Provide ENGINEER with assistance in locating existing facilities, when requested. B. Provide general project review, where required. Page 6 of 19 C. Provide copies of existing facility record drawings. D. Provide existing facility operation data, as available. E. Attendance at project meetings. F. Provide topographic and boundary survey of each project lift station site. Survey shall be provided to ENGINEER in ACAD format. Survey scope shall include but not be limited to the following: ► General site topography including but not limited to: paving, fence, manholes, wetwell, valve box, control panel, landscaping and other above grade features. ► Spot elevations of the site per NAVD 88 Datum. ► Draft existing property lines, RM lines and easements per plat and other recorded documents. G. Assistance in determination of fencing addition feasibility of each site. H. Resident Project Representative Services Services which will be provided by the CITY's resident project representative will include the following: ► Monitor that project is constructed in conformance with the Contract Documents. ► Make periodic on -site field observations of the Contractor's performance. The limits of the authority of the on -site representative are as defined within the Construction Contract Documents. ► Observe any field tests and review the results of tests required of the Contractor by the Contract Documents. ► Assist in the development of punch lists in conjunction with the milestone inspections to determine if the project has achieved Substantial and Final Completion and that the work has been completed in general conformance with the Contract Documents. ► Provide daily reports of construction activity to the ENGINEER on a form provided by the ENGINEER. ► Provide photographs of the work during construction showing typical construction, conflicts with other utilities, installation of new equipment and tie-ins to existing facilities. ► Keep the ENGINEER informed of any changes which need to be made and have the ENGINEER be a part of the change decision process. Page 7 of 19 Be present at all required times for permit compliance_ ARTICLE 3 - TIME OF COMPLETION Table 3 provides the preliminary project schedule based on days from the receipt of the Authorization to Proceed. ARTICLE 4 - PROJECT DELIVERABLES Project deliverables for the project design and construction phases shall be in accordance with Table 4, attached. ARTICLE 5 - PAYMENT AND COMPENSATION As consideration for providing the services enumerated in Article 1, the CITY shall pay the ENGINEER fees as described below: A. Design Phase Forthe services enumerated in Article 1, Tasks D1 through D10, the lump sum fee of $57,160.00. B. Construction Phase For services enumerated in Article 1, Tasks C1 through C12, the estimated not to exceed fee of $45,673.00. Engineering services during construction will be billed on an hourly rate plus direct expenses in accordance with the attached scope of work breakdown. Eckler Engineering will submit monthly invoices payable by person, hours worked, and hourly rates, plus direct expenses for these engineering services. Any unused portion of this estimated not -to -exceed fee will not be billed to the City. These fees have been determined in accordance with the scope of work breakdown attached as Table 5 and 6. The fee does not include the provision of the following items: A. Preparation of permit submittal applications to the City of Tamarac Building Department. B. Easement acquisitions and legal work as required. C. Landscaping, fencing, irrigation system, or site screening system design. D. Design of replacement lift station control panel(s). E. Any expert witness or testimony services. F. Payment of permit fees. Page 8 of 19 G. Services not specifically indicated in this Task Authorization. (Remainder of page left blank intentionally.) Page 9 of 19 ARTICLE 6 - AUTHORIZATION In WITNESS WHEREOF, the parties have made and executed this Agreement on the respective dates under each signature. CITY OF TAMARAC, signing by and through its City Manager, and CONSULTANT, signing by and through its President, duly authorized to execute same. CITY A ��$'��� 0 = ichael C. Cernech, City Manag r Pat Teufel Date City Clerk X4,�� Date � ?Yt a ATTEST: U � vV v (Corpor to Secretary) Douglas K. Hammann Type/Print Name of Corporate Secy. (CORPORATE SEAL) Page 10 of 19 ;,IL7 Eckler Enai eerina. Inc. C par Na je MY A IA,,--,— Signatdre of President/Owner Douglas K. Hammann, P.E. Type/Print Name of President/Owner Date CORPORATE ACKNOWLEDGMENT STATE OF Florida SS COUNTY OF Broward I HEREBY CERTIFY that on this day, before me, an Officer duly authorized in the State aforesaid and in the County aforesaid to take acknowledgments, personally appeared Douglas K. Hammann, of Eckler Engineering, Inc., a Florida Corporation, to me known to be the person(s) described in and who executed the foregoing instrument and acknowledged before me that he executed the same. WITNESS my hand and official seal this day of /i ,24' 1� , 2018. Signature of Notary Public State of Florida at Large t.INDAC. FRACASSO MY COMMISSION#00013498 Linda C. FracaS50 M= EXPIRES. May 1, 2021 „o y, 8w&d1bfUWAMPL&UN6rWltM Print, Type or Stamp Name of Notary Public X Personally known to me or Produced Identification Type of I.D. Produced DID take an oath, or X DID NOT take an oath Y:\Documents\Tamarac\13D\Task Authorizartion 18-19D L5 Generators\Task Authorization\Task Auth 18-19D.wpd Page 11 of 19 TABLE 1 LIFT STATIONS 16A, 34, 37, AND 2E GENERATOR ADDITIONS TENTATIVE LIST OF PROJECT DRAWINGS Drawing Sheet No. Titig General Cover sheet G-1 Project Location Map and Index to Drawings G-2 General Notes and Abbreviations G-3 Mechanical Legends and Symbols G-4 Design Criteria G-5 Sequence of Construction Coordination G-6 LS Locations Map Civil C-1 Generator Installation Site Plan (LS-16A) C-2 Generator and Fuel Tank Slab (LS-16A) C-3 Generator Elevation and Installation Details (LS-16A) C-4 Generator Installation Site Plan (LS-34) C-5 Generator and Fuel Tank Slab (LS-34) C-6 Generator Elevation and Installation Details (LS-34) C-7 Generator Installation Site Plan (LS-37) C-8 Generator and Fuel Tank Slab (LS-37) C-9 Generator Elevation and Installation Details (LS-37) C-10 Generator Installation Site Plan (LS-2E) C-11 Generator and Fuel Tank Slab (LS-2E) C-12 Generator Elevation and Installation Details (LS-2E) C-13 Automatic Transfer Switch Installation Site Plan (LS-18) C-14 Automatic Transfer Switch Installation Site Plan (LS-1813) C-15 Automatic Transfer Switch Installation Site Plan (LS-2A) C-16 Automatic Transfer Switch Installation Site Plan (LS-7E) CD-01 Standard Details - Civil Electrical E-1 Electrical Notes and Legends E-2 Electrical Site Plan (LS-16A) E-3 Proposed One -Line Diagram Modification (LS-16A) E-4 Electrical Site Plan (LS-34)) E-5 Proposed One -Line Diagram Modification (LS-34) E-6 Electrical Site Plan (LS-37) E-7 Proposed One -Line Diagram Modification (LS-37) E-8 Electrical Site Plan (LS-2E) E-9 Proposed One -Line Diagram Modification (LS-2E) E-10 Electrical Site Plan (LS-18) Page 12 of 19 E-11 E-12 E-13 E-14 E-15 E-16 E-17 E-18 ED-1 ED-2 Proposed One -Line Diagram Modification (LS-18) Electrical Site Plan (LS-18B) Proposed One -Line Diagram Modification (LS-18B) Electrical Site Plan (LS-2A) Proposed One -Line Diagram Modification (LS-2A) Electrical Site Plan (LS-7E) Proposed One -Line Diagram Modification (LS-7E) Specific Details - Electrical Standard Details - Electrical Standard Details - Electrical (Remainder of page left blank intentionally) Page 13 of 19 TABLE 2 LIFT STATIONS 16A, 34, 37, AND 2E GENERATOR ADDITIONS TENTATIVE LIST OF PROJECT SPECIFICATIONS SECTION NO. TITLE PART 1 BIDDING REQUIREMENTS (These documents provided by City Purchasing Division) PART 2 CONTRACT FORMS (These documents provided by City Purchasing Division) PART 3 MISCELLANEOUS FORMS/INFORMATION (These documents provided by City Purchasing Division) PART 4 SPECIFICATIONS Division 1 - General Requirements 01005 General Requirements 01010 Summary of Work 01050 Field Engineering 01200 Project Meetings 01300 Submittals 01400 Quality Control 01500 Construction Facilities and Temporary Controls 01505 Mobilization/Demobilization 01700 Contract Closeout 01720 Project Record Documents 01730 Operation and Maintenance Data 01740 Warranties and Bonds Division 2 - Sitework 02020 Existing Utility LocationNerification 02072 Demolition 02200 Earthwork 02500 Restoration and Cleanup 02630 Concrete Sidewalks, Drives, and Curbs 02831 Chain Link Fences and Gates Division 3 - Concrete 03300 Concrete 03600 Grout Page 14 of 19 I Division 4 - Not Used Division 5 - Metals 05500 Fabricated Metalwork and Castings Division 6 - Not Used Division 7 - Thermal and Moisture Protection 07230 Vapor Barrier 07900 Sealants Division 8 - Not Used Division 9 - Protective Coatings 09900 Protective Coatings Division 10 -15 - Not Used Division 16 - Electrical 16000 Electrical General Requirements 16001 Electrical Demolition 16050 Basic Materials and Methods 16204 Generator (Exterior Enclosed) with Base Mounted Tank 16250 Automatic Transfer Switch (Remainder of page left blank intentionally.) Page 15 of 19 TABLE 3 LIFT STATIONS 16A, 34, 37, AND 2E GENERATOR ADDITIONS PRELIMINARY PROJECT SCHEDULE Time to Cumulative Time Activity Complete To Complete (Days) (Days) 1. Notice to Proceed 0 0 2. Site Visit/Information Gathering I Topographic Survey 30 30 3. Submit 90% Drawings and Specifications 60 90 4. Receive CITY Review Comments 14 104 5. Submit 100% Drawings and Specifications 14 118 6. Receive CITY Review Comments 14 132 7. Submit Final Plans and Specifications along with 14 146 permit applications and final cost opinion 8. Permitting 45 191 9. Bidding coordination with Purchasing Division 7 198 10. Bidding and Award Phase 60 258 11. Construction Phase (Final) 270 528 12, Project Closeout 14 542 Detailed schedule will be provided upon receipt of authorization to proceed and will include specific submittal dates. (Remainder of page left blank intentionally.) Page 16 of 19 TABLE 4 LIFT STATIONS 16A, 34, 37, AND 2E GENERATOR ADDITIONS LIST OF PROJECT DELIVERABLES DESIGN PHASE A. 90% Design Submittal (Electronic Submittal) ► One (1) set of 11" x 17" Drawings, 90% Complete ► One (1) set of Specifications, 90% Complete ► 90% Completion Estimate of Probable Construction Cost B_ 100% Design Submittal (Electronic Submittal) ► One (1) set of 11" x 17" Drawings, 100% Complete ► One (1) set of Specifications, 100% Complete ► 100% Completion Estimate of Probable Construction Cost C. Final Design/Permit Application Submittal (Electronic Submittal) ► One (1) set of 11" x 17" Drawings, Final. ► One (1) set of Specifications, Final. ► Final estimate of probable construction cost. BIDDING SERVICES (Part of Design Phase) A. Bidding Coordination Submittal (Electronic Submittal) ► One (1) set of 11" x 17" Drawings (Final). ► One (1) set of Specifications (Final). ► One (1) Final Completion Estimate of Probable Construction Cost. B. Pre -Bid. ► Five (5) CD's with final bid documents for CITY's use during bid phase. Each CD will contain: bid specifications, half-size bid drawings, and full-size bid drawings. All files will be in .pdf format. ► Project Final Documents including drawings on 22" x 34" or 11" x 17" sheets and project specifications on 8-1 /2" x 11" sheets for use by CITY ( City and Engineer). Two (2) sets of project documents, final completion. Page 17 of 19 P. Addenda information as required by the CITY and/or Contractors. C. Post Bid. ► Recommendation of Award Letter. The CITY will award contract and issue Notice of Award. CONSTRUCTION PHASE A. Pre -Construction ► Pre -Construction conference Meeting Agenda and Minutes. ► Four (4) sets of half size (11" x 17") signed/sealed drawings or electronic submittal files(Adobe .pdf) for building permit submittal by CONTRACTOR. ► Three (3) Sets of half size (11" x 1711) drawings and specification booklets for CONTRACTORS use through the construction phase. ► Three (3) sets of drawings (11" x 17") and specifications for CITY's use during construction. ► One (1) sets of drawings (11" x 17").and specifications for sub -consultant's use during construction. B. Shop Drawings P. Copies of approved and final shop drawings. C. Construction Inspection ► Site visit reports will be provided for each site visit in accordance with Task C6 of this Task Authorization. D. Progress Meetings Not applicable. E. Contract Modifications 0. Four (4) copies of all completed contract modifications. F. Pay Requests b. Copies of reviewed and accepted partial and final pay request applications. G. Record Drawings and Project Closeout ► One (1) half size, signed and sealed set of record drawing prints for submittal of permit certification documents to the Building Department. ► One (1) half size, signed and sealed set of prints, one (1) half size set of record drawings, and one (1) copy of AutoCad drawing files on CD for use by CITY. ► Four (4) copies of the certificate of substantial completion and punch lists. Page 18 of 19 H. Special Inspection Not applicable. (Remainder of page left blank intentionally.) YADocuments\Tamarac\BD\Task Authorizartion XX-XXD LS Generators\Task Authorization\Task Auth XX-XXX.wpd Page 19 of 19 CITY OF TAMARAC LIFT STATIONS 16A, 34,37 AND 2E GENERATOR ADDITIONS TASK AUTHORIZATION NO. 18-19D TABLE 5 L DESIGN PHASE DATE: May 16. 2018 TASK DESCRIPTION PERSONNEL a g W w W 2Ee W o W o W .c .a E rc 01 Project Administration I Management 9 9 D2 Data Evaluation and Preliminary Design 12 12 3 03 Not Used C4 Drawings and Engineering 10.75 21.5 120 05 Specification Preparation 14.5 14.5 14.5 06 Not Used D7 Prepare Opinions of Probable Construction Cost 3 6 D8 Bidding Assistance Services 6 0 7 D9 Bid Evaluation and Recommendation of Award Assistants 2 2 010 Submit and Review (Quality Control) 6 4 Used �QlNol Not Used Total Hours Rate Sub -Total Labor 0 63.25 54 0 0 0 0 120 0 0 39.5 E225.00 $204.00 $130.00 $100.00 $85.00 $75.00 $100.00 $93.00 $78.00 $108.00 $80.00 $0.00 $12.903.00 $7,020.00 $0.00 $0.00 WOO $0.00 $11.160.00 $0.00 $0.00 $3.160.00 TOTAL LABOR $34.243.00 II. REIMBURSABLE EXPENSES DESIGN PHASE EXPENSE ITEM EXPENSE TYPE UNIT No. OF UNITS COST PER UNIT TOTALCOST 1 REPRODUCTION Half Size drawings (I I'xl7-) EA 4 $21.50 $86.00 Full Size drawings (22"x34") EA 0 $49.86 $0.00 Specification Booklets EA 4 $50.00 $200.00 CD's EA 5 $20.00 $1D0.00 2 PHOTOCOPIES EA 100 S0.20 $20.00 PLOTTING SETUP 3 22 X 34 (SET UP) EA 43 $3.00 $129.00 11 X 17 (SET UP) EA 86 $3.00 $258.00 TRAVEL 4 MILEAGE MILE 0 $6.545 $0.00 TOLLS EA 0 SOX SUBCONSULTANTS SURVEY LS 0 $0.00 $0.00 ELECTRICAUIBC LS 1 $22,113.63 $22,113.63 5 STRUCTURAL LS 0 $0.00 $0.00 GEOTECHNICAL LS 0 $0.00 E0.00 HYDROGEOLOGIC LS 0 $0.00 $0.00 RADIO SURVEYILICENSINO LS 0 $0.00 $0.00 HVAC LS 0 $O.CO $0.00 TOTAL EXPENSES $22.906.63 GRAND TOTAL $57,149.63 USE $57,150.00 YM000MENT6XTam1ec\442.CI Design Scope CITY OF TAMARAC LIFT STATIONS 16A, 34,37 AND 2E GENERATOR ADDITIONS TASK AUTHORIZATION NO. 18-19D TABLE 6 1. CONSTRUCTION PHASE DATE. May 16, 2018 TASK DESCRIPTION PERSONNEL a a S a n g g - t e - a t E Cl Project AdminislmtionfManagement 9 12 C2 Preconstructlan Activities Priorto NTP 12 6 4 4 C3 Consult and Advise 21 8 10 C4 Review Shop Drawings 10 40 20 C5 Peview, Pay Requests and Schedules 4.5 18 10 C6 Pedann Pedadic end Milestone Ins ectlon a 16 10 C7 Progress meetings - NIA CB Contract Modifications 2 2 2 C9 Prgecl Closeout 6 4 10.75 3 C10 Regulatory Agency Oocumentatlon and Project Closeout Submittals 4 14 6 C71 Special Services 0 0 C12 Special Inspection - NIA Total Hours Rat Sub -Total Labot 0 57.5 Joe 0 0 G 0 24.75 0 0 67 $226.00 $204.00 $130.00 $11 t.00 $100.00 $85.00 $10000 $93.GG $7800 $108.00 $80.00 $0.00 $11.730.00 $14.040.00 $0.00 $0.00 $0.00 1 S000 1 $2.301,75 $0.00 $0.00 $5.360.00 TOTAL LABOR $33.431.75 11. REIMBURSABLE EXPENSES EXPENSE ITEM EXPENSE TYPE UNIT No. OF UNITS COST PER UNIT TOTAL COST 1 REPRODUCTION Half Site Drawings (11"x 1T) FA 5 $25.00 $126.00 Full Size Drawings (22"x34'1 EA 4 $58.00 $232.00 Specification Booklets FA 6 $44.22 $221.10 2 PHOTOCOPIES EA 200 $0.20 S40.00 PLOTTING 3 22 X 34 (SET UP ) EA 0 $15.00 Woo 11 X 17 (SET UP) FA 0 $3.00 $0.00 TRAVEL 4 MILEAGE MILE 30 $0.535 $16.05 TOLLS EA 1 $0.00 $0.00 SUBCONSULTANTS SURVEY LS 0 $0.00 $0.00 ELECTRICAL LS 1 $11606.76 $11,606.76 5 STRUCTURAL LS 0 SO.00 $0.00 GEOTECHNICAL LS 0 $0.00 Woo HYDROOEOLOGIC LS 0 $0.00 $0.00 PERMIT FEES LS 0 $0.00 $0.00 TOTAL EXPENSES $12.240.91 GRAND TOTAL $45,672.66 USE $45,673.00 YI)CaumentslTamaraclBOlTaakAulherilarllea 18-19D LS GeneraturslTask AulhorinbanlSCC SCOPE.xis Project Name LIFT STATIONS 16A, 34, 37 and 2E GENERATOR ADDITIONS Project Number Task Authorization Number 18-19D Date 5/16/2018 City Project Into Tamarac Opinion of probable Construction Cost Prepared By DKH Item Description Sub Total Unit Unit Price Extended Price General 1 `Mobilization / Gen. Requirements 1 LS 12.00% $58,200.00 2 Indemnification 1 LS $100.00 $100.00 3 *As -Built Record Drawings 1 LS 0.50% $2,425.00 4 'Maintenance of Traffic 0 LS 4.00% $.00 5 *NPDES General Construction Permit Compliance 0 LS 0.50% $.00 6 *Existing Utility Location/Identification 1 LS 0.50% $2,425.00 * Calculated using Total of Items below General Total $63 160.00 Generator Addition at the Lift Station Sites 7 Partial site demoltion 4 EA $1,000.00 $4,000.00 8 Earthwork 4 EA $1,000.00 $4,000.00 9 Concrete 4 EA $1,750.00 $7,000.00 10 Generator 4 EA $75,000.00 $300,000.00 11 ATS 4 EA $7,500.00 $30,000.00 12 Site electrical 4 EA $10,000.00 $40,000.00 13 Restoration and cleanup 4 EA $2,500.00 $10,000.00 14 $0.00 $0.00 15 $0.00 $0.00 16 $0.00 $0.00 17 $0.00 $0.00 18 $0.00 $0.00 19 1 .001 $0.00 20 $0.001 $0.00 Generator Additions Total $395,000.00 ATS Addition at the Lift Station Sites 21 Partial site demoltion 4 EA $1,000.00 $4,000.00 22 Earthwork 4 EA $1,000.00 $4,000.00 23 Concrete 4 EA $500.00 $2,000.00 24 ATS 4 EA $7,500.00 $30,000.00 25 Site electrical 4 EA $10.000.00 $40,000.00 26 Restoration and cleanup 4 EA $2,500.00 $10,000.00 27 $0.001 $0.00 28 $0.00 1$0.00 29 1 $0.001 $0.00 30 1 $0.001 $0.00 ATS Additions Total $90,000.00 Subtotal Construction — $548,150.00 Contin enc 1 I LS 1 5% $27,408.00 Total Estimated Project Cost $576,000.00 roject Name ILIFT STATIONS 16A, 34, 37 and 2E GENERATOR ADDITIONS roject Number ITask Authorization Number 18_-19D ate 5/16/2018 Info IOoinion of probable Construction Cost Total I Unit I Unit Price 1 *Mobilization / Gen. Requirements 1 LS 12.00% $39,000.00 2 Indemnification 1 LS $100.00 $100.00 3 *As -Built Record Drawings 1 LS 0.50% $1,625.00 4 *Maintenance of Traffic 0 LS 4.00% $.00 5 *NPDES General Construction Permit Compliance 0 LS 0.50% $.00 6 *Existing Utility Location/identification 1 LS 0.50% $1,625.00 * Calculated using Total of Items below General Total i $42,350.00 Generator Addition at the Lift Station Sites 7 Partial site demoltion 4 EA $1,000.00 $4.000.00 8 Earthwork 4 EA $1,000.00 $4,000.00 9 Concrete 4 EA $1,750.00 $7,000.00 10 Generator 4 EA $35,000.00 $140,000.00 11 ATS 4 EA $7,500.00 $30,000.00 12 Site electrical 4 EA $10,000.00 $40,000.00 13 Restoration and cleanup 4 EA $2,500.00 $10,000.00 14 $0.00 $0.00 15 $0.00 $0.00 16 $0.00 $0.00 17 $0.00 $0.00 18 $0.00 $0.00 19 $0.00 $0.00 20 $0.00 $0.00 Generator Additions Total $235,000.00 ATS Addition at the Lift Station Sites 21 Partial site demoltion 4 EA $1,000.00 $4,000.00 22 Earthwork 4 EA $1,000.00 $4,000.00 23 Concrete 4 EA $500.00 $2,000.00 24 ATS 4 EA $7,500.00 $30,000.00 25 Site electrical 4 EA $10,000.00 $40,000.00 26 Restoration and cleanup 4 EA $2,500.00 $10,000.00 27 1 1 1 $0.00 $0.00 28 $0.00 $0.00 29 $0.001 $0.00 30 $0.001 $0.00 ATS Additions Total $90,000.00 Subtotal Construction IP $367,350.00 Contin enc 1 I LS 1 5% $18,368.00 Total Estimated Project Cost $386,000.00