CITY OF TAMARAC, FLORIDA
RESOLUTION NO. R-2013 - 6�- (T n
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
TAMARAC, FLORIDA, APPROVING AND AUTHORIZING THE
APPROPRIATE CITY OFFICIALS TO SUBMIT AN APPLICATION
TO THE FLORIDA FISH AND WILDLIFE CONSERVATION
COMMISSION FOR FLORIDA BOATING IMPROVEMENT
PROGRAM (FBIP) GRANT FUNDS FOR THE VETERANS' PARK
BOAT DOCK PROJECT IN AN AMOUNT NOT TO EXCEED
$100,000, PROVIDING FOR UP TO A $100,000 MATCH IN
LOCAL FUNDS IN ADDITION TO STAFF TIME FROM THE
PROJECT IN THE EVENT OF APPROVAL OF THE
APPLICATION; PROVIDING FOR ACCEPTANCE OF THE
AWARD AND EXECUTION OF DOCUMENTS UPON
APPROVAL OF THE APPLICATION; PROVIDING FOR
CONFLICTS; PROVIDING FOR SEVERABILITY; AND
PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the City Commission of the City of Tamarac desires to provide its
residents and visitors a higher level of service by enhancing and improving its outdoor
recreation facilities and environment; and
WHEREAS, the Florida Boating Improvement Program (FBIP) grant provides funds to
local governments to improve recreational boating facilities; and
WHEREAS, there is a need for a boat dock and lighting at Veterans' Park; and
Temp Reso. #12313
Page 2
February 28, 2013
WHEREAS, the granting agency requires and the City is willing to match the FBIP
grant program request of up to $100,000 with up to $100,000 in local funds in addition to staff
time from the project in the event of approval; and
WHEREAS, it is a requirement of the grant program that this Resolution be adopted
and become an official part of the grant application; and
WHEREAS, the Director of Financial Services and Director of Public Services
recommend approval; and
WHEREAS, the City Commission of the City of Tamarac deems it to be in the best
interest of the citizens and residents of the City of Tamarac to submit an application to the
Florida Fish and Wildlife Conservation Commission for FBIP grant funds to enhance
recreational boating opportunities at Veterans' Park.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY
OF TAMARAC, FLORIDA:
Section 1: That the foregoing "WHEREAS" clauses are hereby ratified and confirmed as
being true and correct and are hereby made a specific part of this Resolution. All exhibits
attached hereto and referenced herein are expressly incorporated and made a specific part of
this Resolution.
Temp Reso. #12313
Page 3
February 28, 2013
Section 2: The appropriate City Officials are HEREBY authorized to submit a Florida
Boating Improvement Program (FBIP) grant program application in an amount not to exceed
$100,000 to the Florida Fish and Wildlife Conservation Commission, providing for the required
match of up to $100,000 in local funds in addition to staff time from the project for the provision of
the Veterans' Park boat dock project. A copy of said application form is attached hereto as
Exhibit A.
Section 3: Upon approval of the application, the appropriate City officials are HEREBY
authorized to accept the award and execute the necessary documents following legal review
and approval.
Section 4: An appropriation for the receipt and expenditure for this grant will be included in a
budget amendment prior to November 30, 2013 pursuant to F.S. 166.241(2)
Section 5: All Resolutions or parts of Resolutions in conflict herewith are HEREBY
repealed to the extent of such conflict.
Section 6: If any clause, section, or other part or application of this Resolution is held by
any court of competent jurisdiction to be unconstitutional or invalid, in part or application, it
shall not affect the validity of the remaining portions or application of this Resolution.
Section 7: This Resolution shall become effective immediately upon its passage and
adoption.
Temp Reso. #12313
Page 4
February 28, 2013
PASSED, ADOPTED AND APPROVED this )- 7daY of -f'1-� , 2013.
BETH TALABISCO
MAYOR
ATTEST:
__L2 A'�
PATRICIA TEOFEP CMC
INTERIM CITY CLERK
RECORD OF COMMISSION VOTE:
MAYOR TALABISCO `,<7
DIST 1: COMM. BUSHNEL < <�
DIST 2: COMM. ATKINS-GR-��..X
DIST 3: COMM. GLASSER
DIST 4: V/M. DRESSLER i
I HEREBY CERTIFY THAT I HAVE
APPROVED THIS RESOLUTION
AS TO FORM
mped, ip_� 3 14,_.
SAMU S. GORE=
CITY -ATTORNEY
�xA
(DFlorida Fish and Wildlife Florida Boating Improvement Program
.N1yFWC;...n1
Conservation CommissionConsrvatGrant Application for Boating Access Facilities
FOR OFFICE USE ONLY
Grant Application Number 7 Date Received:
Fill in all sections that annly — Leave all other sections blank
I — APPLICANT INFORMATION
a. Applicant:
b. Federal Employer Id. No.:
c. Project Manager Name:
Project Manager Title:
d. Mailing Address:
City: Zip Code:
e. Shipping Address:
City: Zip Code:
f. Telephone: Fax:
Email:
g. District Numbers: U.S. Congressional:
State Senate: State House:
II — PROJECT SUMMARY
a. Project Title:
b. Type of Application: ❑ New (never considered before)
❑ Reconsideration ❑ Phased Continuation —Phase No.:
TIER -I
TIER -II
c. Project Category:
❑ A —Public Launching Facilities
❑ A —Boat Ramps, Piers, and Docks
❑ B — Public Launching Facilities
d. Project Cost: Total Cost: $
Amount Requested: $
e. Project Summary:
FWC/FBIP-B (03/12) Page 1 of 7 68-1.003, F.A.C.
III - FACILITY INFORMATION
a. Facility Name:
b. Type of Facility:
❑ Existing Boat Ramp / Public Launching Facility
❑ Existing Marina / Tie-up / Overnight Moorage Facility
❑ Proposed Boat Ramp / Public Launching Facility
❑ Proposed Marina / Tie-up / Overnight Moorage Facility
❑ Other:
c. Facility location:
County:
Water body:
Township: Section:
Range:
Latitude: N de,g. min. sec.
Longitude: W dep. min. sec.
Facility Street Address or Location:
d. Upland Ownership:
❑ Public - Fee Simple ❑ Public — Lease Number of Years Remaining in Lease:
Name of Owner:
e. Is this facility open to the general public? ❑ Yes
❑ No
f. Estimate Percent (%) Use of Launching Facility: % Motorboats/Sailboats % Non -Motorboats
g. Day Use, Parking or Launch Fee Amount: $
Tie-up/Overnight Moorage: $
h. Number of Launch Lanes:
Condition: ❑ New ❑ Good ❑ Average ❑ Poor
i. Number of Boarding Docks: Length: Ft.
Condition: ❑ New ❑ Good ❑ Average ❑ Poor
Type of docks: ❑ Fixed Wooden ❑ Fixed concrete
❑ Floating ❑ Other :
j. Number of Boat Trailer Parking Spaces:
Condition: ❑ New ❑ Good ❑ Average ❑ Poor
k. Tie-up Dock or Moorage: Ft or Slip
Condition: ❑ New ❑ Good ❑ Average ❑ Poor
Type of docks: ❑ Fixed Wooden ❑ Fixed concrete
❑ Floating ❑ Other:
1.Other Facility Attributes:
Restroom: ❑ Yes ❑ No ❑ Proposed
Other:
Pump out or Dump Station: ❑ Yes ❑ No
Other:
m. Names of adjacent boating facilities, public and private (ramps, tie-up facilities/marinas) within a 10-mile radius.
Name Distance
Name Distance
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
FWC/FBIP-B (03/12) Page 2 of 7 6S'-I 003_ r A c
IV - PROJECT DESCRIPTION
a. List Primary Need for Project: ❑ Safety
❑ High Demand by Users
❑ Age -end of Useful Life
Recommended by FWC Staff
❑ Environmental Needs of the Area ❑
❑ Lack of In-house Capability
❑ Other:
b. Need Statement:
c. Approach (Scope of Work): Describe the project's scope of work by providing a list of tasks and deliverables:
d. Project Benefits:
FWC/FBIP-B (03/12) Page 3 of 7 68-1.003, F.A.C.
V — BUDGET
a. Has a detailed cost estimate been developed for this project? If yes, attach a copy to application.
❑ Yes, Preliminary ❑ Yes, Final ❑ No
b. PROJECT COST: NON -CASH MATCH
Cost Item
Applicant
Share
Other Share
(List below in
Section VI)
Do Not Use
This Column
TOTAL
Administration
$
$
$
Project Management
$
$
$
In -Kind Engineering
$
$
$
In -Kind Labor
$
$
$
In -Kind Materials
$
$
$
In -Kind Equipment
$
$
$
Total Non -Cash Match
$
S
S
c. PROJECT COST: CASH FUNDS
Cost Item
Applicant
Share
Other Share
(List below in
Section VI)
FBIP Grant
Share
TOTAL
Administration / Project Management
$
$
$
$
Design / Engineering
$
$
$
$
Permitting
$
$
$
$
Construction / Repair: Boat Ramps
$
$
$
$
Construction / Repair: Lifts, Hoists, Marine Railways
$
$
$
$
Construction / Repair: Piers or Docks
$
$
$
$
Construction / Repair: Parking
$
$
$
$
Construction / Repair: Restrooms
$
$
$
$
Other:
$
$
$
$
Other:
$
$
$
$
Other:
$
$
$
$
Other:
$
$
$
$
Other:
$
$
$
$
Total Cash Funds
S
$
S
$
d. TOTAL COST: (non -cash match + cash funds) $ $ S $
FWC/FBIP-B (03/12) Page 4 of 7 68-1.003, F.A.C.
VI — OTHER SOURCE OF FUNDS (Partnerships)
a. Funding source / Agency:
b. Type of funding: ❑ Federal grant
❑ State/Local grant
❑ Loan
c. Grant Name:
Amount $
d. Approval Status: ❑ Approved ❑ Pending
❑ Intend to Apply, Date:
a. Funding source / Agency:
b. Type of funding: ❑ Federal grant
❑ State/Local grant
❑ Loan
c. Grant Name:
Amount $
d. Approval Status: ❑ Approved ❑ Pending
❑ Intend to Apply, Date:
a. Funding source / Agency:
b. Type of funding: ❑ Federal grant
❑ State/Local grant
❑ Loan
c. Grant Name.
Amount $
d. Approval Status: ❑ Approved ❑ Pending
❑ Intend to Apply, Date:
II VII - PROJECT ENGINEERING AND CONSTRUCTION II
a. Who is or will be completing project design/engineering?
❑ Applicant's Own Staff
❑ Consulting Engineers
❑ N/A (Materials or Equipment Purchase)
❑ Other:
b. Level of engineering completed at time of application:
❑ None
❑ Conceptual (Master Plan Phase)
❑ Preliminary
❑ Final (Ready to Bid)
VIII - PERMITS
Submitted
Approved
N/A
a. Florida Department of Environmental Protection
❑
❑
❑
b. Florida Fish and Wildlife Conservation Commission*
❑
❑
❑
c. U.S. Army Corps of Engineers
❑
❑
❑
d. Local and Others (If needed)
❑
❑
❑
* Note: Projects involving mooring buoys must be permitted pursuant to Chapter 68D-23, F.A.C.
FWC/FBIP-B (03/12) Page 5 of 7 68-1.003, F.A.C.
X - BOATER SAFETY
a. Explain how the project may affect boater safety whether positively or negatively.
FWC/FBIP-B (03/12) Page 6 of 7 68-1.003, F.A.C.
XI - APPLICATION ATTACHMENTS CHECKLIST
Submit one (1) signed original plus two (2) photocopies of the application with attachments and an electronic copy on CD.
Inc.
- - - Required Attachments - - -
❑
a. Cover Letter: application transmittal cover letter (Identify priority rank with multiple applications).
❑
b. Application: One (1) application with original signature from authorized individual.
❑
c. Resolution: An adopted resolution, by the Governing Body, authorizing that the Project Manager has the authority to
apply for and administer the grant on behalf of the applicant. If the Applicant is applying on behalf of another public
entity, then a Memorandum of Understanding between the Applicant and the public entity must also be submitted.
❑
d. Boundary Map: indicate boundary of the project area.
❑
e. Site Control Documentation: (e.g. a deed, lease, results of title search, etc. for the project site.)
❑
f. Existing Condition Photographs (sufficient to depict the physical characteristics of the project area)
❑
g. Aerial Photographs (marked with the approximate boundaries of the project site)
❑
h. Detailed Cost Estimate: Cost estimate in the form of a formal bid, written quote from proposed vendor or an
engineer's cost estimate.
❑
i. Navigational Chart: An 8.5" x I I" photocopy of a current NOAA North American Datum 83 nautical chart (provide
the NOAA chart name and number) indicating the precise location of the project site.
- - - For Construction Grants - - -
❑
j. Permits: Photocopies of necessary project permit(s) or permit application(s). If exempt, provide notification of
exemption from permitting agency.
...
-- Optional Attachments - - -
❑
k. Plans: preliminary design/engineering plans (if completed).
❑
I. Support/Opposition: Attach letters of known public support or known public opposition.
APPLICANT SIGNATURE
Application is hereby made for the activities described herein. I certify that I am familiar with the information contained
in the application, and, to the best of my knowledge and belief, this information is true, complete, and accurate. I further
certify that I possess the authority including the necessary requisite property interests to undertake the proposed activities.
I also certify that the Applicant's governing body is aware of and has authorized the Project Manager as the official
representative of the Applicant to act in connection with this application and subsequent project as well as to provide
additional information as may be required. By signature below, the Applicant agrees to comply with all applicable
federal, state, and local laws in conjunction with this proposal and resulting project so approved.
Print/Type Name
Applicant Signature
Title
Date
WARNING: "Whoever knowingly makes a false statement in writing with the intent to mislead a public servant in the performance of
his or her official duty shall be guilty of a misdemeanor of the second degree, punishable as provided in s. 775.082 or s. 775.083." §
837.06, Florida Statutes.
NOTE: Instruction and further information regarding this application and the Florida Boating Improvement Program can be found in
the Florida Boating Improvement Program Guidelines or you may contact the Program Administrator at: Florida Fish and Wildlife
Conservation Commission, Florida Boating Improvement Program, 620 South Meridian Street, Tallahassee, FL 32399-1600; or call
(850) 488-5600; or email fbip@MyFWC.com.
FWC/FBIP-B (03/12) Page 7 of 7 68-1.003, F.A.C.
FLORIDA FISH AND WILDLIFE CONSERVATION COMMISSION
FLORIDA BOATING IMPROVEMENT PROGRAM
Instructions for completing the Grant Application for Boat Access Facilities
General Instructions:
• Submit one (1) signed original and two (2) copies.
• Submit an electronic copy of application on CD.
• Staple application in upper left-hand corner, or clip with one binder clip. DO NOT
SPIRAL BIND OR PLACE IN A THREE-RING BINDER OR REPORT COVER.
• Please place a tabbed divider between each attachment.
• Please make all photocopies of attachments on paper no larger than I I" x 17".
I — APPLICANT INFORMATION
a. Applicant:
Enter the name of the county, municipality, or other
governmental entity applying for the grant.
b. Federal Employer Id. No.:
Enter the applicant's Federal Employer Identification
(FEID) Number. Payment will be sent to the address
associated with this FEID number.
c. Project Manager Name:
Enter the name and title of the person in charge of the
Title:
project. All correspondence will be sent to this person.
d. Mailing Address:
Enter the mailing address for the Project Manager. All
correspondence will be sent to this address.
e. Shipping Address:
If mailing address is a P.O. box, please include a street
address for overnight deliveries.
f. Telephone No.:
Enter the telephone number, fax number, and email
Fax No.:
address where the Project Manager may be contacted
E-mail:
during regular business hours.
g. District Numbers:
Enter the number of the U.S. Congressional district, State
House district, and State Senate district where the project
is located.
n
Page 1 of 4
11�
n
II — PROJECT SUMMARY
a. Project Title:
Provide a brief title for the project.
b. Type of Application:
Check "New" if you have never applied for FBIP funding
for this project. Check "Reconsideration" if you have
applied before but did not receive funding. Check
"Phased Continuation" if the project has previously
received FBIP funding.
c. Project Category:
Check only one project category. Refer to the guidelines
for project category descriptions. Application will
compete only against other applications within the same
project category. The Commission reserves the right to
re -assign the application to a different project category to
maximize funding.
d. Project Cost:
Enter total amount of project cost, including only the
eligible project elements where grant funds will be used.
Enter the amount of funds requested from FBIP (rounded
to the nearest dollar).
e. Project Summary:
Provide a brief description of the goal of the project, the
work to be done and the expected outcome or final
product.
III - GENERAL FACILITY INFORMATION
Describe existing conditions by checking all that apply. For new facilities, provide
information as facility is proposed to be and check "New" for questions about condition of
facility.
IV - PROJECT DESCRIPTION
a. List Primary Need for Project:
Check the category that is most applicable.
b. Need Statement:
Briefly describe why this project is needed. Explain any
existing problems and how this project will correct the
problem.
c. Approach(Scope of Work):
Describe in detail the exact work to be completed. For
example, Task 1 — Construct one -lane, concrete boat
ramp, Task 2 — Construct 20 boat/trailer parking spaces.
d. Project Benefits:
Describe how this project will enhance boating in the
local community.
Page 2 of 4
V — BUDGET
a. Has a detailed cost estimate
Indicate whether a preliminary or final cost estimate has
been developed for this
been developed. If yes, attach a copy of the estimate to
project?
the application.
Enter amount of in -kind match for each cost item.
b. PROJECT COST - NON-
Amounts in "Other" column should include in -kind match
CASH MATCH*
from any third -party agreements (provided by someone
other than the applicant). *Please note: All applications
must include some form of non -cash match.
c. PROJECT COST - CASH
Enter amount of funding to be provided by the applicant
FUNDS
and other sources. Enter the amount of funding requested
in the column labeled "FBIP Grant Share."
d. TOTAL PROJECT COST
Sum of non -cash match and cash funds for each column.
VI - OTHER SOURCE OF FUNDS (Partnerships)
Include information on funding from sources other than FBIP or the applicant. Enter
information for each funding source.
a. Funding Source / Agency:
Enter the name of the funding source or the partner
b. Type of funding:
Check source of funds: Federal grant, State/Local grant, or
loan.
c. Grant Name:
Enter the name of the grant program (if applicable).
d. Approval Status:
Enter status of grant/loan application. If "Intending to
Apply", enter date of application deadline.
VII - PROJECT ENGINEERING AND CONSTRUCTION
a. Who is or will be completing project I Please check as appropriate.
design/engineering?
b. Level of engineering completed at time of Please check as appropriate. If engineering is
application: complete (conceptual, preliminary, or final),
please include a copy of the plans with your
application.
n
Page 3 of 4
,^
n
11 1
VIII — PERMITS
a. Florida Department of
Environmental Protection
b. Florida Fish and Wildlife
Conservation Commission
c. U.S. Army Corps of Engineers
d. Local and Others (If needed)
Check status of all permit applications. If project type does
not require permits, or project is exempt from permitting
requirements, check "N/A". If applicable, attach a
photocopy of all permits or permit applications. If project is
exempt, attach a copy of exemption notification.
Note: Projects involving mooring buoys must be
permitted pursuant to Chapter 68D-23, F.A.C.
IX - ENVIRONMENTAL ASSESSMENT
a. Will the project significantly Explain how the project will have a significant or adverse
or adversely affect the affect on the environment and include information on the
environment? impacts to water quality, wetlands, seagrasses, imperiled
b. If Yes, please explain key species, etc.
issues and describe any
mitigation actions Dronosed.
X — BOATER SAFETY
a. Explain how the project may Provide explanation of how the project may improve boater
affect boater safety whether safety (i.e. increased education, increased law enforcement,
positively or negatively. etc.) or, explain any potential boater safety hazards and how
they will be corrected. Also, please indicate if the project
will have no effect on boater safety.
XI — APPLICATION ATTACHMENTS CHECKLIST
Indicate which attachments have been included with the application. Required attachments must
be included or application will be deemed incomplete. Optional attachments may be omitted.
Please place a tabbed divider between each attachment. Submit one (1) original (with original
signature) and two (2) photocopies of the entire application with attachments. (Only one (1)
copy of the permits and site control documentation is necessary.)
Completed applications should be in the following order: Cover Letter, Application Form,
Attachments in the order they are listed on the checklist.
Page 4 of 4