Loading...
HomeMy WebLinkAboutCity of Tamarac Resolution R-2009-059Temp. Reso. #11606 April 14, 2009 1 CITY OF TAMARAC, FLORIDA RESOLUTION NO. R-2009-L/ A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF TAMARAC, FLORIDA, AUTHORIZING THE APPROPRIATE CITY OFFICIALS TO EXECUTE TASK AUTHORIZATION NO. 09-04E WITH ECKLER ENGINEERING, INC., TO PROVIDE PROFESSIONAL SERVICES FOR THE DESIGN OF A NEW CLEARWELL AT THE WATER TREATMENT PLANT; INCLUDING PREPARATION OF DETAILED PLANS AND SPECIFICATIONS FOLLOWED BY PERMITTING AND BIDDING ASSISTANCE, IN ACCORDANCE WITH THE CITY'S CONSULTING ENGINEERING AGREEMENT AS AUTHORIZED BY RESOLUTION NO. R-2006-131, FOR AN AMOUNT NOT TO EXCEED $139,000.00; APPROVING FUNDING FROM THE APPROPRIATE BUDGETED UTILITIES OPERATIONAL ACCOUNTS; AUTHORIZING THE APPROPRIATE CITY OFFICIALS TO ADMINISTER THE CONTRACT; PROVIDING FOR CONFLICTS; PROVIDING FORSEVERABILITY; AND PROVIDING FORAN EFFECTIVE WHEREAS, the City of Tamarac owns, operates and maintains the water supply, treatment, and distribution systems; and WHEREAS, the City of Tamarac operates a 60,000 gallon clearwell which is an integral part of the Water Treatment Plant; and WHEREAS, the recently completed 2.0 MG Water Storage Tank and WTP Improvement Project (Bid No. 04-17B) required the Contractor to provide cleaning and structural integrity inspections of all finished water facilities within the City of Tamarac in accordance with FAC 62-555.350; and WHEREAS, Crom Engineering and Construction Services Inc., inspected the 60,000 gallon clearwell and found it to have severe structural deterioration and in danger of Temp. Reso. #11606 April 14, 2009 2 ' structural failure ("Exhibit 1"); and WHEREAS, Eckler Engineering Inc., was approved by City Commission under Task Authorization Number 06-05E to provide professional services for design, permitting, and construction management for the Structural Repair of the existing WTP Clearwell for an amount not to exceed $39,300.00. As part of the preliminary engineering design, Eckler Engineering, Inc., completed a detailed Inspection Report of the WTP clearwell on August 17, 2006 followed by a memo on September 26, 2006 which detailed three (3) options to complete Structural Repairs of the existing WTP Clearwell and a fourth option to construct a new clearwell ("Exhibit 2"); and WHEREAS, the City Utilities Department reviewed the four (4) Clearwell options with Eckler Engineering on October 10, 2006 and came to the conclusion that capital dollars would be best spent constructing a new clearwell (Option 4) designed with the capacity to ' meet both existing and proposed Florida Department of Environmental Regulations. The Structural Repair of the WTP Clearwell Project was cancelled by the City of Tamarac Utilities Engineering Division on October 11, 2006 ("Exhibit 3" ); and WHEREAS, the City requires the service of a consulting firm knowledgeable in this area and capable of providing professional services for the design, permitting and bidding assistance of the Water Treatment Plant Clearwell Project; and WHEREAS, Eckler Engineering, Inc., possesses the required knowledge and experience to provide the professional engineering services associated with the Water Treatment Plant Clearwell Project; and WHEREAS, Eckler Engineering, Inc., has been pre -qualified as an approved consultant for engineering services by the City of Tamarac as authorized by Resolution No. I R-2006-131; and Temp. Reso. #11606 April 14, 2009 3 WHEREAS, it is the recommendation of the Director and Assistant Director of Utilities that Task Authorization No. 09-04E from Eckler Engineering, Inc., be approved, executed and funded; and WHEREAS, the City Commission of the City of Tamarac, Florida, deems it to be in the best interest of the citizens and residents of the City of Tamarac to accept and execute Task Authorization No. 09-04E ("Exhibit 4") with Eckler Engineering, Inc., to provide engineering services for the design, permitting and bidding assistance of the Water Treatment Plant Clearwell Project for an amount not to exceed $139,000.00 and to provide funding from the appropriate Operational accounts. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF TAMARAC, FLORIDA, THAT: SECTION 1: The foregoing "WHEREAS' clauses are hereby ratified and confirmed as being true and correct and are hereby made a specific part of this resolution. All exhibits attached hereto are incorporated herein and made a specific part of this resolution. SECTION 2: The appropriate City Officials are hereby authorized to accept and execute Task Authorization No. 09-04E with Eckler Engineering, Inc., to provide engineering services for the design, permitting and bidding assistance of the Water Treatment Plant Clearwell Project, in accordance with the City's Consulting Engineering Agreement as authorized by Resolution No. R-2006-131 on July 12, 2006, for an amount not to exceed $139,000.00; and SECTION 3: The $139,000.00 is approved to be funded from the 2009 Operational accounts. Temp. Reso. #11606 April 14, 2009 4 ' SECTION 4: The City Manager, or his designee, are hereby authorized to make changes, issue change orders not to exceed $30,000.00 per Section 6-156 (b) of the City Code, and close the contract award including, but not limited to making final payment within the terms and conditions of the contract and within the contract price. SECTION 5: All resolutions or parts of resolutions in conflict herewith are hereby repealed to the extent of such conflict. SECTION 6: If any clause, section, other part or application of this Resolution is held by any court of competent jurisdiction to be unconstitutional or invalid, in part or application, it shall not affect the validity of the remaining portions or applications of this Resolution. SECTION 7: This Resolution shall become effective immediately upon its passage and adoption. PASSED, ADOPTED AND APPROVED this/ 9 day of�`. 2009. BETH FLANSBAUM -TALABISCO ATTEST: MAYOR RECORD OF COMMISSION VOTE: _J1,MARION SWENSON, CMC MAYOR FLANSBAUM-TALABISCO CITY CLERK DIST 1: COMM BUSHNELL DIST 2: VM ATKINS-GRAD DIST 3: COMM GLASSER DIST 4: COMM. DRESSLER Q- I HEREBY CERTIFY that I have approved this RESOLUTION as to form. SAMUEL S. GOREN ' ) `CITY ATTORNEY Tank Inspection Report City of Tamarac 0.06-MG Ground Storage Tank Tamarac, FL January 20th, "EXHIBIT 1" TR 911606 Pr6tYCEP11UNIAKEN ONAKE CORRECTIONS NOTED J'iE.'InCTED OREVISEr.i1DRESUBMIT OSUBIdIT SPECIFIED ITEM {h in 1 -s only for g"wel conformance wtih the V1;r r,0ne8pt 01 the project and Conetal comp!iar1ce with ine information given in the e0111iart 5aLanents.I Any aruon <hawn is subject to the requirements of [he plans and spacifications. Contractor is responsible foi dimemwo,4 which shall be, confirmed and correlated' at the lob site, fabrication rrocm;s ob ,r,d at constructimi, :eordination of his wuil, r.i b the t all otnei "wades, ano the satisfactory perforrne,rci 0; hie work _ Crom Engineering & Construction Services, Inc. Jeffery D. Malpass, P.E. President Irvin C. Rubin Project Manager IJREim ENGINEERING Ei GEINSTRNCTINN SERVICES, INC. 250 SW 3Gth Terrace o Gainesville, Florida 32G07 ^ 352-548-3345 ^ Fax 352-548-344G TANK INSPECTION REPORT 1.0 Executive Summa Crom Engineering and Construction Services, Inc (CECS) conducted an inspection of the 60,000-gallon clearwell in Tamarac, Florida on January 20rh 2006. The goal of the inspection was to review the status of the tank and its structural integrity, and to determine what measures, if any, are necessary to bring the tank up to present codes and standards so that the longest useful life of the tank can be realized in meeting the intent of Florida Administrative Code Chapter 62-555.350. Irvin Rubin, CECS Project Manager, performed the inspection with the assistance of Wendell Swilley from Underwater Services International, Inc. His findings were reviewed by Jeffery D. Malpass, P.E. and sealed. The findings of the wet inspection revealed significant deterioration of the clearwell top slab as well as several supporting beams (See Video and Field Inspection Report for specific locations). Two beams in particular show cracking throughout the length of the beam 4 to 5 inches from the bottom of the beam indicating that the beam bottom reinforcing is corroding. This corrosion has resulted in the concrete below the bottom reinforcing spalling from the rest of the beam. The underside of the clearwell top slab has extensive spalling. The slab has exposed reinforcement bars which have completely deteriorated and no longer support the slab. As a result of the findings, CECS recommends a comprehensive concrete restoration of the clearwell's top slab and beams including the replacement of reinforcing bars. The complete deterioration of the #7 reinforcing bars in the clearwell top slab is of concern regarding the slab's structural integrity. CECS recommends placing temporary shoring inside the clearwell until the necessary repairs can be made to the structure. 2.0 Scope of Work The purpose of the inspection is to investigate the structural integrity of the 0.06- MG clearwell. The investigation included the interior and exterior walls of the tank, the roof slab, floor, and tank accessories. The inspection was a visual survey of the structure with no invasive procedures employed. The tank was inspected in accordance with AWWA D110 and ACI 350 to evaluate the present condition of the tank structure. The tank was cleaned prior to the interior inspection. The tank was physically examined for any visible problems such as leaks or cracks, any location that was questionable, was looked at closer to determine the extent of the problem. The wall was observed for any deterioration, cracking, spalled concrete, and signs of corrosion or any indicators of existing problems such as efflorescence or damp spots. The inspector was provided access to the concrete roof slab. The concrete slab was inspected for any cracking, efflorescence, spalled concrete, and signs of corrosion or other indicators of existing problems. Tank accessories were looked at to determine the extent of the weathering of the fiberglass and the condition of the bolts, fasteners and the screens. All penetrations were checked for signs of leakage into the tank. All areas of concern were noted and mapped in the inspector's field notes. A dive team was given access to the interior of the tank and a video record was made of the interior inspection. The process was monitored on the surface by real time closed circuit video. The interior wall and floor were observed for cracking, spalled concrete, and signs of corrosion, or other indications of existing problems. Piping and internal accessories were checked for corrosion and condition of their supports, bolts, and anchors. The tank was fully surveyed and a record was made of all observations. Photographs were taken as an additional record of the inspection. 3.0 Field Investigation See attached Field Inspection Report. 4.0 Conclusions and Recommendations The inspection of the 0.06-MG tank at the City of Tamarac's Water Treatment Plant has been carried out in accordance with AWWA D110 and fulfills the requirements of FAC 62-555.350. The inspection of the cast in place clearwell revealed serious deterioration issues with the clearwell roof slab and supporting beams. 2 (1) Condition of clearwell roof slab: Extensive deterioration of the concrete roof slab was observed during the inspection. The two east most bays of the main room in the clearwell exhibit the most severe degradation. Concrete has spalled off the bottom mat of steel, exposing the reinforcing and resulting in complete disintegration of the steel. Consequently, the load carrying ability of the #7 bars spaced at 6.5 inches running north - south has been compromised. CECS recommends placing temporary shoring inside the clearwell to support the damaged slab. Further deterioration of the slab is inevitable and necessary repairs should be made to prolong the useful life of the tank. As a result, CECS recommends a comprehensive concrete restoration of the clearwell slab. (2) Condition of clearwell roof slab support beams: The support beams also show signs of severe deterioration. Two beams in particular show cracking throughout the length of the beam 4 to 5 inches from the bottom of the beam indicating that the beam bottom reinforcing is corroding. This corrosion has resulted in the concrete below the bottom reinforcing spalling from the rest of the beam. CECS recommends placing temporary shoring inside the clearwell to support the damaged beams. Beam bottom reinforcing steel is now exposed to the destructive elements of the tank and further deterioration of the beams will be accelerated, amplifying the importance of swift action to make necessary repairs. As a result, CECS recommends a comprehensive concrete restoration of the clearwell supporting beams. (3) Window to clearwell: A gap between the plexi-glass cover and the clearwell wall on the east wall of the main room was also noted by the inspector (See Figures 3 and 4). Contaminants and insects can enter the tank through this opening and affect the water quality. CECS recommends sealing this gap. Since CECS' inspection was a visual survey of the structure without any invasive or destructive procedures or test, CECS cannot offer an opinion on the condition or performance of the covered or hidden elements of the structure not visible from the surface. The proceeding report is submitted for your review and discussion. We would be pleased to discuss the results with you. If you have any questions or concerns, please do not hesitate to contact us. V Respectfully submitted, CromEngineering and Construction Services, Inc. Jeffery D. Malpass, P.E. President Mgt Figure 1 - Location of 0.06 MG clearwell Figure 2 - Exterior of facility pump building above clearwell Figure 3 - View of window to clearwell Figure 4 - View of gap between plexi-glass window and building Figure 5. Top of slab covering the 0.6-MG Clearwell. C Figure 6. Cleaning robot used by AMPS to remove sediment from tank floor. Sediment was as much as 18-inches deep in some spots. No Text =xax / , Y�AtiM'S"Ne9y4^•.i*NT.P_Fn�� .., ,: TANK DETAILS Location Owner Engineer Diameter (ft) Volume Inspector(s) CRDM ENGINEERING AND CONSTRUCTION SERVICES, INC. 259 SW 36th Terrace Gainesville, Fl. 32607 352.548.3349 - FAX 352.548.3449 Tamarac Utilities West Water Treatment Plant Irvin C. Rubin Date: 1-20-06 Yes No Comments/Photos FOUNDATION 1 Is the tank backfilled? X 2 Does the tooter appear to be level? N/A 3 Are there any gaps between the wall and the footer? N/A 4 Is the Tooter undermined anywhere? N/A 5 Floor/wall connection monolithic? Yes No Comments/Photos FLOOR 1 Has the tank floor been cleaned? 2 Waterstop type 3 Are there any visible cracks on the Floor? 4 Are there any rough spots on the floor? X X Cast -in -place detail X X 5 Are there any pipe penetrations through Floor? X (size, distance above floor, etc.) 6 Are there any sumps? (size and depth) X Additional Comments: Yes No Comments/Photos INTERIOR ROOF SLAB 1 Is there any exposed rebar? X See Video and attached drawing for locations 2 Is there any exposed mesh? X 3 Are there any stalled areas? X See Video and attached drawing for locations 4 Was the dome painted? (condition) X Additional Comments: The two east most bays of the main room have severe deterioration of the roof slab. There are large areas of spelled concrete with exposed rebar. Many of the reinforcement bars have completely corroded through. Yes No Comments/Photos BEAMS 1 Is there any exposed rebar? X See Video and attached drawing for locations 2 Are there any cracks? X See Video and attached drawing for locations 3 Are there any spatted areas? X See Video and attached drawing for locations Additional Comments: Three beams have large cracks which run the entire length of the beam approximately 4 to 6 inches from the bottom of the beam. The cracks range from hairline to 1/8" wide. Yes No Comments/Photos INTERIOR WALL 1 Are there any hollows? X 2 Are there any cracks? X 3 Are there stains on the wall? X 4 Was the wall painted? (Condition) X Additional Comments: Interior wall appears to be in good condition. Yes No Comments/Photos EXTERIOR ROOF SLAB 1 Are there any chips and spalls? X 2 Are there any cracks? X 3 Are there any flat spots? X 4 Are there any humps? _ X Additional Comments: Exterior of slab appears to be in good condition 'There is a gap between the plexi-glass window and the tank wall which should be sealed in order to keep outside contaminants and insects out of the clearwell - See Figures 3 and 4. VO..a MT.nR W,0 gal NORTH TANK FLOOR INTERIOR NORTH WALL. INTERIOR EAST WALL ^ CRAI'K X: PATTERN CROCKING O HOLLOW AREA �% EFFLORF5CENCE �,% CONCNhI'f$PALL � PEELING PAINT/COATING EXP(YSED MESH / ROSI'SPoIS INTERIOR SOUTH WALL INTERIOR WEST WALL NORTH 1 Volume a Tank 6G.GW gal UNIFORM RUST SPOTS THROUGHOUT ENTIRE UNDERSIDE OF ROOF FROM REBAR CHAIRS CRACKS IN BEAM WITH RUST COLORED STAINS -NO OELAMINATION NOTED DETERIORATING BEAM -CRACK RUNS ENTIRE LENGTH OF BEAM 4 TO fi INCHES FROM BOTTOM ON BOTH SIDES OF BEAM - BOTTOM SECTION OF BEAM H45 DEIAMINATED AND 6 FgLLOW ACCESS HATCH SPALLING WITH EXPOSED REW DETERIORATING BEAM - CRACK RUNS ENI IRE LENGTH OF BEAM 4 TO6INCHES FROM BOTTOM OIV EAST SIDE ix E%wSEo. DEIEHIOMTED REbW MRQIfi4X1T FMIgE PAY UNDERSIDE OF TANK ROOF & SEAMS REMgTHRCWFINI .IRE PAY UNDERSIDE OF ROOF SLAB IN POOR CONDUKNJ IN THESE SAYS CRACK RUNNING 5 to 6 INCHES OFF BOTTOM OF SEAM WITH SECTIONS OF OBLAMIN4TED CONCRETE �— CRACK K% PATTERN CRACKING O HOLLOW AREA EPFLORRS ENCE CONCREIESPALL D PEELING PAINT COATING E%POSED MESH/ RUSTOIS "EXHIBIT 2" TR #11606 ECKL ER ENGINEERING, INC. CONSULTING CIVIL ENGINEERS September 26, 2006 442-003.01 Mr. James Moore, P.E. Assistant Director of Utilities City of Tamarac Utilities Department 6001 Nob Hill Road Tamarac, FL 33321 Dear Mr. Moore Reference: Structural Repairs of WTP Clearwell P. O. No. 091259 The attached Report presents the findings of the August 14, 2006 engineering inspection of the Clearwell at the Water Treatment Plant. The water level in the clearwell was lowered to allow Doug Hammann and Ben Kough of Eckler Engineering and Gene Sanders, our structural consultant from Jenkins and Charland Engineers, to examine the condition of the concrete and reinforcing steel in the tank. This inspection was a follow-up to the DEP mandated inspection of finished water tanks by divers which had revealed deterioration of the concrete and reinforcing steel. The inspectors found cracking of the concrete in one column and five beams. The observed cracking and spalling was caused by corrosion which expands the reinforcing steel. It was apparently accelerated by exposure to high chlorine concentrations during the water disinfection process. Significant spalling of the concrete has occurred in two of the eight concrete ceiling bays. Spalling occurs as the cracks in the concrete grow, causing pieces of the concrete cover to break away. This spalling has exposed severely damaged (corroded) reinforcing bars. In one area, five adjacent parallel steel bars are visible, and corroded or missing. The inspectors also found hundreds of rust spots on the ceiling throughout the tank caused by corrosion of the steel chairs (brackets) used to support the reinforcing steel mat during placement of the concrete. Although the corrosion has not advanced enough to cause cracking of the concrete, since the chairs are in contact with the reinforcing steel, each rust spot represents a potential path for corrosion to reach the rebar. The structural integrity of the clearwell is important not only because it is a key element in the finished water process but because it is part of the foundation for the water plant control building. The clearwell was designed in 1969 as part of a one story structure but in 1990, a second floor was later added. Gene Sanders' structural evaluation of the tank's condition and his recommendations for repair are presented in his attached letter dated September 12. These conclusions are based on Mr. Sanders 30 years of South Florida experience with corroded reinforcing steel in concrete structures. Selection of the optimum repair procedure to restore and preserve the structural integrity of the clearwell must consider the required longevity, repair cost and duration and its impact on plant Celebrating our 21st Year of Service to South Florida 4700 RIVERSIDE DRIVE, SUITE 110 9541510.4700 CORAL SPRINGS, FL 33067 Pnnte on Recycled Paper FAY9541755-2741 Mr. James Moore, P.E. September 26, 2006 Page 2 operations. Since the clearwell is the final collection vessel for all finished water from the filters, if it is removed from service for repair, the packaged filters would be shutdown and by-pass pumps would be required in the Greenleaf filter. Bypass pumping costs during clearwell repairs are estimated to be $50,000 to $100,000. Four repair options are being considered. Option 1, recommended by our structural engineer, utilizes conventional repair techniques to restore the original design strength of the slab. Option 2 would wall off and backfill the two east bays (1 & 2) which are the most heavily damaged. This would reduce the clearwell volume by 25% to 45,000 gallons but the transfer and backwash pumps would remain operational in their current location. Option 3 would minimize repairs in the clearwell and assumes that the top mat of reinforcing steel is not damaged by corrosion, The damaged beams and spalled slab portions would be chipped and patched and the entire ceiling structure would be sprayed with a tank coating to shield the reinforcing steel from moisture. The slab will be cored to investigate the condition of the covered reinforcing steel. Option 4 would make no repairs to the clearwell and continue it's use with regular inspections while a new clearwell is constructed west of the entrance drive. The new clearwell would be sized and designed to be utilized as a component of future water treatment plant construction. The estimated cost of the proposed options are not yet available, but the relative cost is indicated on a scale from 1 (least expensive) to ten (most expensive). OPTION (DESCRIPTIONS BELOW) ESTIMATED COST (SCALED ESTIMATED LIFE EXPECTANCY COMMENTS 1. Full restoration 8 10 years 2. Abandon Bays 1 & 2 6 10 years 3. Limited repair 5 2- 10 years Six month inspections 4.New Clearwell 10 30 years Option 1: All slab bays, beams and columns which display rust stains will be stripped of surface concrete (typically to 2 1/2") to expose sound reinforcing steel. Rebar will be exposed a minimum of V on all sides and sandblasted to white metal. Steel which is less than 70% of it's original diameter must be replace with a minimum overlap of 36" at each end of the damaged area. All exposed rebar will receive two coats of Armatec 110 to retard corrosion. New concrete will be shotcreted to provide a minimum of 2" of concrete cover over the steel. Provide shoring for the slab and beams during construction. Option 2: Abandon Bays 1 & 2 extending the east finished water and overflow pipes 30' into Bay 3. Construct concrete isolation/support walls between Bays 2 and 3 and 2 and 6 then backfill bays 1 & 2. Sandblast, chip or grind all rust stained concrete spots to sound reinforcing steel and prime to prevent future corrosion. Cover all exposed steel with cementitious grout. The cracked beams (Bays 4 & 7) and column (Bay 8) will be stripped of bottom surface concrete (typically 21/2") to expose the reinforcing steel. Rebar will be exposed a minimum of 1" in all dimensions, sandblasted Mr. James Moore, P.E. September 26, 2006 Page 3 and coated. Add new rebar where required. The exposed rebar will be covered with a minimum of 2" of new concrete. Provide temporary shoring for the slab and beams under repair. Option 3: The two slabs and 3 cracked beams in Bays 1 & 2 Bay 8 shall be stripped of the bottom surface concrete (typically 2.5") to expose the reinforcing steel. Rebar will be sand blasted, replaced as necessary and coated then covered with 2" of concrete (shotcrete) over the steel. The cracked beams (Bays 4 & 7) and column (Bay 8) will be chipped to a 1" depth to investigate the subsurface conditions. Additional chipping or stripping of additional concrete may be required at the direction of the Engineer to expose the rebar. Where the rebar is exposed, it will be primed and covered with 2" of concrete (shotcrete). All other areas clearwell will be sandblasted to remove rust spots. All exposed steel will be primed with Armatec 110. Additional chipping or grinding may be required to remove rusted steel at some locations. Exposed steel will be coated and covered with 2" of concrete (shotcrete). Two coats of polyamidoamine epoxy will be applied to seal all ceiling and column surfaces. Provide temporary shoring for slabs and beams under repair. Option 4: Abandon the clearwell after constructing a new clearwell west of the entrance drive then relocate the transfer and backwash pumps with the intent that this new structure would be utilized in future new water treatment plant construction. Continue operation of the clearwell during construction with inspections every 3 months to monitor further deterioration. Eckler Engineering recommends the repair outlined in Option 3. This option is anticipated to be the least expensive, provides immediate repair of the damaged structural elements and investigation, preservation and monitoring of the other corrosion sites in the wetwell. After you have had a chance to review the options and recommendations contained herein, we would like to meet with you and other applicable Tamarac Utilities staff to determine the direction to proceed at this time. Tentatively, we would like to meet the week of October 9, 2006. Please review these findings, then we will meet with you to answer questions. If you require additional information, please do not hesitate to contact me. Sincerely, Douglas K. Hammann, P.E. Encl. cc: Mr. John Harvey Mr. Gene Sanders, P.E. 442-003 Clearwell Repair.wpd INSPECTION REPORT WATER TREATMENT PLANT CLEARWELL forthe CITY OF TAMARAC Prepared By ECKLER ENGINEERING, INC. 4700 Riverside Drive Coral Springs, Florida 33067 EE No. 7802 August 2006 Douglas Hammann, P.E., 50589 INSPECTION REPORT CLEARWELL REPAIR TAMARAC WATER TREATMENT PLANT DATE: August 17, 2006 PROJECT: 442-003.01 REFERENCE: Structural Inspection of Clearwell Concrete ATTENDEES: Mr. Gene Sanders, P.E., Jenkins and Charland Mr. Doug Hammann, P.E., Eckler Engineering Mr. Ben Kough, P.E., Eckler Engineering Water flow into the Clearwell was shutdown and it was pumped down to a depth of I foot. The inspectors entered the Clearwell and examined the concrete surfaces and evaluated and documented the areas damaged by corrosion of the reinforcing steel. Longitudinal concrete cracking,'/2" to 6" from bottom of beam Concrete spalled from ceiling exposing corroded rebar. Cracking 2-3" from the bottom of the beam Exposed rebar with less than'/2" of concrete cover. Dark gray remains of previous patching All eight bays of the Clearwell showed rust in 100-500 spots, each locating corroding reinforcing steel. On five of the beams and one column, longitudinal cracking has occurred. At over one hundred locations the concrete has spalled, exposing the remains of the rusted rebar. Some locations show evidence of prior patching efforts. Predominant rust spot patter❑ from exposed or minimally covered rebar Transfer pump - exposed and corroded rebar CHEMICAL FEED LOCATIONS The chlorine diffuser is a vertical 24" long, 3/4" pipe located in the northeast corner of the wetwell (no photo) as shown on Drawing 2. The ammonia diffuser is the horizontal assembly shown below and located on Drawing 2. MISCELLANEOUS FINDINGS Rusted metallic grout Rusted steel bracket Rusted steel conduit support Rusted, abandon unistrut Spalled concrete (16"x 6" x1.25") and rusted rebar BAY 7 1 11 t I 1 I CORROSION ON BOTTOM OF CLEARWELL TOP SLAB SCALE : 1/4" = V-0" (REFLECTED CEILING PLAN) LEGEND RUST SPOTS SPALLS CRACKS EXPOSED RUST SPOTS SPALLED CONCRETE ON INLET BOX DSCN: B. KOUCH VERIFY SCALE JtN KINA & CITY ®F TkLMARAC CHARLAND Dwc No a1 r—t"�{ ewronA�co ECOCLE{4 ENGINEERING, INC. DR: R.P. ® =ad ...w ..Am CLEARWELL 383G N.W. 53rd $h..l PROJ ND 942-00].D01 CHK: DA.WIANN W Is ONE INCH ON FORT LApERDALE FL 3330G STRUCTURAL REPAIR OF TOP SLAB DAMAGE 4200 RIVERSIDE DRIVE, SUITE 110 — CORAL SPRINGS, FL. 33067 ORIGINAL DRAWINO. Ea ^b30 (934) aea_)JD DONALD ECKLER, P.E. (954) 510-4J00 — EB No. 7803 ppyp: pA.ECKLER Kum SCALES WTP CLEARWELL AS uECEBYAv. NO DATE REVISIONS BY APVD CONSULTANT FL a189]4 PATE AUC. 2008 JENKINS & CHARLAND INCORPORATED Consulting Engineers Structural - Civil Tuesday, September 12, 2006 Mr. Doug Hammann Eckler Engineering, Inc 4700 Riverside Drive Coral Springs, FL 33067 Ref: Tamarac Water Treatment Plant Clear Water Tank Dear Doug The present condition and possible courses of action to restore the structure of the clear water tank at the above referenced facility are presented below. The condition of the underground tank was determined by visual observations. No destructive investigations were performed. The below ground tank is under a two story building. Deterioration of the concrete structure of the tank ceiling which is the ground floor slab has advanced to the point where there are indications of corrosion of the steel embedded in the concrete slab, concrete beams, concrete walls and the upper portion of the concrete columns. Corrosion of reinforcing steel embedded in new concrete is resisted by the chemical properties of the new concrete. As the concrete ages the chemistry at the surface is changed by the infusion of chlorine. The depth of chorine penetration increases as the concrete ages. After passage of sufficient time the penetration depth reaches the reinforcing steel and corrosion begins. Rust, the product of corrosion, occupies a greater volume than the original steel. As the corrosion progresses the intimate bond between steel and concrete is compromised and the surface concrete is initially cracked and then spalled off. The time from original construction to the onset of corrosion is typically measured in several tens of years whereas the time from the onset of corrosion to the point where the structural integrity of the slab is compromised progresses at a significantly faster rate. It is difficult to predict the rate of deterioration of strength once corrosion begins but it could be as little as a fraction of a year but is unlikely to be more than a year or two. Rust stains indicate the chemistry of the concrete has changed and is no longer preventing corrosion. Cracks indicate that sufficient rust has formed to both compromise the bond between concrete and steel and the volume of the rust is sufficient to overcome the tensile strength ofthe concrete. As the cracks increase eventually pieces of the surface concrete will be isolated and become completely detached. Observations revealed evidence of corrosion ranging from rust stains to cracks and spelling in all of the slab soffits. Corrosion has progressed in the beams and at the tops of the columns to the extent necessary to form cracks in the surface concrete. To restore the structure to its original strength, the aged concrete must be removed from around the corroded reinforcing and replaced with new concrete. The reinforcing steel may be re -used after the rusted surface is removed and cleaned to allow re -bonding of the steel to the new concrete. Additional reinforcing may be required if the area of steel after cleaning has been reduced significantly by rusting. 3590 Northwest 56 Street Fort Myers Fort Lauderdale, FL 33309 Sarasota (954) 484-7777 Fax: (954) 484-7834 Fort Pierce JENKINS & CHARLAND INCORPORATED Consulting Engineers Mr. Doug Hammann 09/12/06 Page 2. Structural - Civil Failure to provide at least one inch of concrete in all directions around the cleaned reinforcing will significantly compromise the corrosion protection provided by the new concrete. There are two alternatives to restoring the concrete slab to its original design strength. These are: 1) Remove the bottom surface of the concrete slab and the bottom layers of reinforcing steel. Make the excavated surface smooth with cementitious grout and design a mat of carbon fiber mesh with sufficient strength to replace the original reinforcing. 2) Remove the bottom surface of the concrete slab and the bottom layers of reinforcing steel. Introduce new columns and associated foundations spaced sufficiently close to allow the remaining concrete slab, which now has a reduced thickness, to act as un- reinforced concrete. The spacing of the new columns and foundations is dependent on the thickness of the concrete that is remaining after the removal of the bottom layer of reinforcing. Both of these alternatives will probably be more expensive and / or labor intensive than the conventional remedial work described above. Other alternatives have been suggested that modify the chemistry of the concrete to restore its ability to prevent corrosion. While many of these processes work as advertised none of them has the ability to remove the rust from the reinforcing steel nor restore the bond between concrete and steel which is essential to restore the slab strength. These processes are only effective if they are employed before the onset of corrosion. It is recommended that the slab. beams and columns be repaired by removing the surface concrete, cleaning the existing reinforcing steel and placement of additional steel if necessary and forming and pouring new concrete on the slab soffit. Any compromise of this procedure will result in a repair that is difficult to determine the useful life but will likely be much less than 10 years. Very truly yours, Jenkins and Charland, Inc Gene S Sanders, P.E. Vice President Gene S Sanders FL P.E.26590 9/ 26/ 200614:33 3590 Northwest 56 Street Fort Myers Fort Lauderdale, FL 33309 Sarasota (954) 484-7777 Fax:(954) 484-7834 Fort Pierce Utilities Administration TO: FROM: DATE: SUBJECT: City of Tamarac "Committed to Excellence... Always" MEMORANDUM Mr. Douglas K. Hammann, P.E. "EXHIBIT 3" TR #11606 Eckler Engineering, Inc. 4700 Riverside Drive, Suite 110 Coral Springs, FI 33067 James T. Moore, P.E. Asst. Director of Utilities— City of Tamarac October 11, 2006 Structural Repairs of WTP Clearwell Cancellation of PO # 091259 As we discussed at our meeting on October 10, 2006, the City of Tamarac - Utilities has decided to cancel the PO #091259 with Eckler Engineering, Inc. for Structural Repairs of the existing WTP Clearwell. We feel that capital dollars would be best spent in constructing a new clearwell designed with the capacity to meet both existing and proposed DEP regulations. The repairs outlined in your September 26, 2006 memo, which detailed the options for the Structural Repairs of the WTP Clearwell, would result in too much WTP clearwell downtime and potential cost overruns. In addition, the bypass pumping systems that would need to be installed would put the WTP operation at greater risk with the clearwell out of service. We will keep you informed regarding our timetable to complete the new clearwell. Please submit your invoices for engineering costs incurred on this project through October 10, 2006 at your earliest convenience. Please contact me if you have any further questions. Sincerely, James T. Moore CC: Gary Wainwright - City of Tamarac Raymond E. Gagnon, P.E. - City of Tamarac John Harvey - City of Tamarac Keith Glatz - City of Tamarac Donald A. Eckler, P.E. -Eckler Engineering, Inc. 6001 Nob Hill Road ® Tamarac, Florida 33321-6200 ■ (954) 724-2400 0 Fax (954) 724-2406 is www.tomorac.org Equal Opportunity Employer "EXHIBIT 4" TR #11606 TASK AUTHORIZATION NO. 09-04E: SCOPE OF SERVICES WATER TREATMENT PLANT CLEARWELL ADDITION INTRODUCTION On March 11, 2009 Eckler Engineering met with the City of Tamarac to discuss the finished water clearwell and transfer pumping improvements planned for the CITY's Water Treatment Plant. The general scope of this project is preliminary design, preparation of drawings and specifications and engineering services during the construction phase of this project. This project will also be coordinated with and include applicable recommendations from the CITY's Water Master Plan, dated January 22, 2009. In accordance with our project planning meetings, the following design scope is recommended and included in this project proposal: New reinforced concrete clearwell structure. The anticipated design criteria for this structure shall be as follows: Design flow rate of 15.0 MGD. Incorporate transfer and backwash pumping systems into the structure. Incorporate area to blend lime softened water with future membrane permeate, prior to final disinfection contact volume of the proposed clearwell. Incorporate provision to receive membrane permeate from future degasification tower(s) and blowers to be located adjacent to the proposed clearwell. Final disinfection contact volume shall be based on CT value to meet 4-log virus deactivation based on free chlorine disinfection. New filter effluent transfer pumps. The final number of variable speed transfer pumps to produce the firm design capacity of 15.0 MGD will be determined during the preliminary design. This determination shall be based upon specific pumping conditions as determined from the pump manufacturer's data and in order to meet electrical power availability from the existing motor control center. New filter backwash pumps. Two (2) constant speed backwash pumps with a firm capacity of 2000 GPM. This flow rate is equivalent to a filter backwash rate of 20 GPM/SF. 4. New filter effluent and backwash supply piping improvements to facilitate the new clearwell installation. 5. Conversion of the existing filters to influent rate of flow control. This will allow for greater flexibility in the filter effluent piping design and operation. The existing Greenleaf filter operation shall remain as existing. Greenleaf Filter may require revision to effluent weirs. 6. Relocation of existing NaOCI and ammonia piping to service the new clearwell. Page 1 of 17 7. New concrete and CMU power distribution and VFD equipment enclosure at the proposed clearwell. This enclosure will house the proposed transferpump(s) VFD's, backwash pump(s) MCC, primary power distribution for the clearwell systems and space for future facility improvements. 8. New raceways for new and proposed electrical loads and instrumentation needs. Raceways will originate from the existing MCC area for power and from the existing control room area for instrumentation. 9. Coordinate and provide control strategies for modifications to the CITY's existing SCADA system to incorporate the new clearwell, transfer pumping system revisions and backwash pumping revisions. 10. New field instruments for the revised operations including clearwell level transducer(s), filter level transmitters, free and total chlorine residual analyzers and other field instruments as necessary for a properly functioning instrumentation and control system. 11. Yard piping modifications and improvements to facilitate the new clearwell and pumping systems. 12. Provide new electrical power distribution from the existing gear to facilitate the proposed improvements. Power distribution improvements for the future LPRO system are not included within this scope. 13. Modifications to existing on site sanitary collection and transmission system to facilitate the proposed improvements. 14. Elimination of the existing clearwell, transfer pumps and process water (W2) pump after new facilities are in operation. 15. Revision to provide process water supply (W2) from the existing high service pumps. 16. Design of general aesthetic and site work to be included at this site including but not limited to the following: General site cleanup and restoration. Painting of interior walls, piping, conduits, and miscellaneous items that are proposed or disturbed by progress of work. Painting of exterior walls piping, conduits, and miscellaneous items that are disturbed by the progress of the work. Architectural improvements related to scope of work. Relocation of existing employee parking area impacted by the work. Miscellaneous site work improvements inclusive of grading, sidewalks, pavement restoration and sodding. The preliminary task order Opinion of Probable Construction Cost for the above referenced improvements is estimated at $1,200,000 to $1,500,000. (These figures represent the budget cost range and cannot be warranted due to market construction cost conditions.) Page 2 of 17 The engineering tasks associated with this project are presented below: ARTICLE 1 - SCOPE OF SERVICES Design Phase Task D1 - Project Administration/Management This task focuses on the administration of the project including project setup, client interface and general project management and administration. Task D2 - Data Evaluation and Preliminary Design This task focuses on obtaining the necessary preliminary information required to prepare detailed engineering plans and specifications. A. Meet with appropriate CITY staff to discuss project requirements. B. Visit the site and review pertinent features that may impact design and/or construction. C. Collect data available for the existing facilities, including field conditions, record drawings, connection locations, and information on other potentially impacted utilities. D. Prepare scope of services, coordinate and complete geotechnical work as may be applicable. E. Prepare scope of services, coordinate and complete additional topographic survey as may be applicable. Task D3 - Preliminary Design Report (Memorandum) This task consists of the appropriate level of engineering to analyze and prepare final design requirements for this project. A. Evaluate the data assembled under Task D2 for the establishment of the final design criteria for the proposed revisions. B. Prepare a preliminary design memorandum for this project. The preliminary design report (memorandum) will be prepared for this project in accordance with Florida Department of Environmental Protection Rules FAC Chapter 62-555. The report (memorandum) shall detail all proposed modifications at the facility. Preliminary design requirements for all system components to be modified or completed as part of this project will be presented as part of the Preliminary Design Report (memorandum). These improvements will include civil, structural, architectural, electrical, mechanical, and instrumentation requirements. Page 3 of 17 C. The preliminary design memorandum shall include 50% complete drawings and specifications. D. Prepare a preliminary opinion of probable construction cost for the improvements proposed for this project. E. Meet with appropriate CITY staff to discuss and finalize the project design and parameters. Task D4 - Drawings and Engineering This task consists of the engineering and the development of plans necessary to construct this project. A. Prepare detailed drawings for the proposed work discussed previously within this Exhibit. A tentative list of final design drawings to be developed for this project is presented in Table 1. Drawings will be prepared using drafting standards and standard details as developed by Eckler Engineering, Inc. Task D5 - Specification Preparation This task consists of the preparation of specifications necessary to construct this project. A. ENGINEER shall prepare technical specifications required forthis project in Division 1 through Division 16. These specifications, utilizing the CSI format, will be prepared and will consist of written technical descriptions and materials, equipment and construction systems, standards and workmanship required for this project as developed by Eckler Engineering. A tentative list of specification sections to be prepared for this project is presented in Table 2. B. The City of Tamarac standard bidding requirements, contract forms and miscellaneous forms/information required for this project shall be utilized. Consultant shall provide the Cityof Tamaracwith project specific information for the preparation of bidding and contract documents required for this project. Task D6 - Permit Preparation Assistance This task consists of preparing the following permit application submittals: A. Broward County Health Department (BCHD)/ Florida Department of Environmental Protection (FDEP) permit to construct minor WTP improvements. Any additional permits required beyond the above will be considered as outside the scope of this proposal. Task D7 - Final Opinion of Probable Construction Cost Prepare the 50%, 90%, 100%, and final levels of Opinion of Probable Construction Cost for new facilities and improvements proposed under this project. Page 4 of 17 Task D8 - Bidding Assistance Services This task shall include work necessary to assist CITY with the bidding of this project. This work may include the following: A. Assist with the coordination of the bidding documents and the advertisement for bid and respond to communication from contractors and issue addenda information as required. Provide up to twenty (20) sets of bid documents for distribution by the CITY to potential bidders. B. Attend the pre -bid meeting and distribute the minutes of the meeting to bidders. C. Respond to written questions by potential bidders and, if needed, assist the CITY in issuing addenda. D. Attend the bid opening and tabulate the bids as provided by interested contractors. Task D9 - Bid Evaluation and Recommendation of Award Assistance This task shall consist of the review and evaluation of the bids and the recommendation of a bidder for award of contract to the CITY. Task D10 - Submit and Review (Quality Control) The ENGINEER will make the following submittals at various completion levels of this project for the purpose of CITY's review and comment for coordination and quality control. A review meeting will be requested following each submittal to discuss and receive comments from CITY. The CITY's comments shall be incorporated into revisions prior to the next subsequent quality control submittal. Quality control submittals for this project are anticipated at the following completion levels: A. Preliminary Design Report (memorandum) and 50% Drawings and Specifications B. 90% Drawings and Specifications. C. 100% Drawings and Specifications. The ENGINEER will incorporate the agreed -upon revisions made by the CITY. A total of three (3) meetings with the CITY is the level of effort for this Task. Task D11 - Regulatory Agency Permit Fees ENGINEER shall pay all permit fees required by the applicable regulatory agencies during the design phase of the project. Construction Phase A scope of services proposal for engineering services during construction will be developed at a later date when requested by the City of Tamarac. Page 5 of 17 Project Deliverables Project deliverables for the project design and construction phases shall be in accordance with Table 4, attached. ARTICLE 2 - DATA OR ASSISTANCE TO BE PROVIDED BY CITY A. Provide assistance with regulatory agencies. B. Provide ENGINEER with assistance in locating existing facilities, when requested. C. Provide general project review, where required. D. Provide copies of existing facility record drawings. E. Provide copies of existing SCADA system as-builts. ARTICLE 3 - TIME OF COMPLETION Table 3 provides the preliminary project schedule based on days from the receipt of the Authorization to Proceed. ARTICLE 4 - PAYMENT AND COMPENSATION As consideration for providing the services enumerated in Article 1, the CITY shall pay the ENGINEER fees as described below: A. Design Phase For the services enumerated in Article 1, Tasks D1 through D11, the lump sum fee of $139,000. These fees have been determined in accordance with the scope of work breakdown attached as Table 5. The fee does not include the provision of the following items: 1. Preparation of permit submittal applications to the City of Tamarac Building Department. 2. Any expert witness or testimony services. 3. Design of improvements to the existing emergency and primary power systems. 4. Engineering services during construction. 5. Any hydrogeologic work required for the design of dewatering systems or the evaluation of the impact on construction dewatering systems for contamination sites within a quarter mile radius of the project site. Page 6 of 17 6. Landscaping and irrigation system designs. ARTICLE 5 -AUTHORIZATION In WITNESS WHEREOF, the parties have made and executed this Agreement on the respective dates under each signature. CITY OF TAMARAC, signing by and through its Mayor and City Manager, and CONSULTANT, signing by and through its President, duly authorized to execute same. ATTEES�T, :: Marion Swenson, CIVIC City Clerk '� Date ATTEST: (Corporate Secretary) Donald A. Eckler Type/Print Name of Corporate Secy. (CORPORATE SEAL) Page 7 of 17 CITY OF TAMARAC Beth Flansbaum-Talabi co, Mayor Date Jeffr�Miller'; City Manager i` dl 1' Date Approved as to form and legal sufficiency: dam [Goren, City Attorney EJ5 Date Eckler Engineering Inc. Company Name ✓`"'w'.cu^ vim^ Signature of President/Owner Donald A. Eckler, P.E. Type/Print Name of President/Owner Date CORPORATE ACKNOWLEDGMENT STATE OF Florida SS COUNTY OF Broward I HEREBY CERTIFY that on this day, before me, an Officer duly authorized in the State aforesaid and in the County aforesaid to take acknowledgments, personally appeared Donald A. Eckler, of Eckler Engineering, Inc., a Florida Corporation, to me known to be the person(s) described in and who executed the foregoing instrument and acknowledged before me that he executed the same. WITNESS my hand and official seal this day of �rp�c(� /D 2009. ... 'Signature of Notary Public UNDA C. FRACASSO State of Florida at Large ,lisreo Comm#DD0855027 y.�Expires 5/1/2013 Linda C. Fracasso Florida Notary Asm., J,, ro Print, Type or Stamp ..................................... Name of Notary Public X Personally known to me or Produced Identification Type of I.D. Produced DID take an oath, or X DID NOT take an oath Y:\Documents\Tamarac\BD\WTP Clearwell Addition\Task Auth 09-04E.wpd Page 8 of 17 TABLE 1 WATER TREATMENT PLANT CLEARWELL ADDITION TENTATIVE LIST OF PROJECT DRAWINGS Drawing Sheet No. Title General Cover sheet G-1 Index to Drawings and Project Location Map G-2 General Notes and Abbreviations G-3 Mechanical Legends and Symbols G-4 Architectural and HVAC Legends G-5 Process and Instrumentation Legend G-6 Electrical Notes and Legends G-7 Overall Plant Flow Schematic G-8 Design Criteria (Sheet 1) G-9 Design Criteria (Sheet 2) Civil C-1 Site Survey C-2 Overall Site Plan and Boring Locations C-3 Paving and Grading Plan Key Map C-4 Paving and Grading Site Plan (Sheet 1) C-5 Paving and Grading Site Plan (Sheet 2) C-6 Existing Clearwell System Demolition Plan and Sections C-7 Existing Clearwell Demolition Details CD-1 Standard Details - Civil CD-2 Standard Details - Civil Architectural A-1 Existing Control Building 1" Floor Modifications A-2 Electrical Building Floor and Roof Plans A-3 Electrical Building Architectural Elevations A-4 Existing Facilities Painting Plan A-5 Finish Schedules A-6 Door and Hardware Schedules AD-1 Standard Details - Architectural Structural S-1 New Electrical Building Floor and Roof Plans S-2 New Electrical Building Sections S-3 New Electrical Building Structural Elevations Page 9 of 17 S-4 Clearwell Foundation Plan S-5 Clearwell Top Plan S-6 Clearwell Sections S-7 Clearwell Sections S-8 Clearwell Sections and Details S-9 Existing Clearwell Basin Modifications SD-1 Standard Details - Structural SD-2 Standard Details - Structural Mechanical M-1 Piping Schedule and General Mechanical Notes M-2 Hydraulic Profile M-3 Yard Piping Key Map M-4 Yard Piping Plan (Sheet 1) M-5 Yard Piping Plan (Sheet 2) M-6 Yard Piping Plan (Sheet 3) M-7 Yard Piping Details M-8 Clearwell Equipment Plan M-9 Clearwell Sections M-10 Clearwell Sections and Details M-11 Clearwell Sections and Details M-12 Existing Transfer and Backwash Pump Station Modifications M-13 Process Piping Profiles M-14 Sanitary Profiles MD-1 Standard Details - Mechanical MD-2 Standard Details - Mechanical MD-3 Standard Details - Mechanical MD-4 Standard Details - Mechanical MD-5 Standard Details - Mechanical Instrumentation 1-1 Process and Instrumentation (Sheet 1) 1-2 Process and Instrumentation (Sheet 2) 1-3 Process and Instrumentation (Sheet 3) ID-1 Standard Details - Instrumentation and Controls Electrical E-1 Electrical Site Demolition Plan E-2 Electrical Site Installation Plan E-3 Existing Transfer and Backwash Pump Demolition Plan E-4 New Clearwell Electrical Plan E-5 New Clearwell Lighting and Grounding Plan E-6 Transfer Pump and Backwash Pump Station Electrical Plan E-7 Plant One -Line Diagram Power (Sheet 1) E-8 Plant One -Line Diagram Power (Sheet2) E-9 Riser Diagram and Conduit Schedule Page 10 of 17 E-10 Transfer Pump VFD Schematics and Details E-11 Existing PLC 1/0 Modifications (Sheet 1) E-12 Existing PLC 1/0 Modifications (Sheet 2) E-13 Clearwell - ACP (Sheet1) E-14 Clearwell - ACP (Sheet2) E-15 New Electrical Building One Line Diagram Power E-16 Electrical Building Electrical Equipment Plan E-17 Electrical Building Lighting and Receptacle Plan E-18 Electrical Building Grounding Plan E-19 Panelboard Schedules E-20 PLC Arrangement Diagram ED-1 Standard Details - Electrical ED-2 Standard Details - Electrical ED-3 Standard Details - Electrical (Remainder of page left blank intentionally) Page 11 of 17 TABLE 2 WATER TREATMENT PLANT CLEARWELL ADDITION TENTATIVE LIST OF PROJECT SPECIFICATIONS SECTION NO. TITLE PART 1 BIDDING REQUIREMENTS (These documents provided by City Purchasing Division) PART 2 CONTRACT FORMS (These documents provided by City Purchasing Division) PART 3 MISCELLANEOUS FORMS/INFORMATION (These documents provided by City Purchasing Division) PART 4 SPECIFICATIONS Division 1 - General Requirements 01005 General Requirements 01010 Summary of Work 01050 Field Engineering 01200 Project Meetings 01300 Submittals 01400 Quality Control 01500 Construction Facilities and Temporary Controls 01505 Mobilization/Demobilization 01700 Contract Closeout 01720 Project Record Documents 01730 Operation and Maintenance Data 01740 Warranties and Bonds Division 2 - Sitework 02072 Demolition 02200 Earthwork 02500 Restoration and Cleanup 02510 Asphaltic Pavement and Base 02630 Concrete Sidewalks, Drives and Curbs Division 3 - Concrete 03100 Formwork 03200 Concrete Reinforcement Page 12 of 17 03251 Expansion and Construction Joints 03300 Concrete 03315 Prestressed Composite Tank 03410 Structural Precast Hollow Core Planks 03600 Grout Division 4 - Masonry 04100 Mortar 04200 Concrete Unit Masonry Division 5 - Metals 05500 Fabricated Metalwork and Castings 05516 Ladders 05520 Handrails and Railings Division 6 - Wood and Plastic 06611 Fiberglass Weir Plates Division 7 - Thermal and Moisture Protection 07230 Vapor Barrier 07533 Thermoplastic Single -Ply Membrane Roofing System 07900 Sealants Division 8 - Doors and Windows 08120 Aluminum Doors and Frames 08710 Finish Hardware Division 9 - Finishes 09201 Portland Cement Plaster (Stucco) 09900 Protective Coatings Division 10 -Specialties 10199 Miscellaneous Building Specialties Division 11 - Equipment 11037 Vertical Turbine Pumps -General 11037-1 Vertical Turbine Pumps -Specific 11037-2 Vertical Turbine Pumps -Specific Division 12 - Not Used Page 13 of 17 Division 13 - Special Construction 13700 Process Instrumentation and Controls 13710 Programmable Logic Controller 13711 Existing PLC/SCADA System Modifications 13720 Variable Frequency Drives Division 14 - Conveying Systems - Not Used Division 15 - Mechanical 15005 Ductile Iron Pipe (Water) 15029 Testing and Disinfection (Pipelines, Structures and Equipment) 15100 Manually Operated Valves 15105 Self -Contained Automatic Process Valves 15400 Plumbing 15800 Air Conditioning Division 16 - Electrical 16000 Electrical General Requirements 16001 Electrical Demolition 16050 Basic Materials and Methods 16110 Lightning Protection 16160 Panelboards 16345 Short -Circuit Coordination Study and Arc Flash Hazard Study 16460 Dry Type Transformers 16921 480 - Volt Motor Control Center Appendices Appendix A - Report of Geotechnical Exploration (Remainder of this page left blank intentionally.) Page 14 of 17 TABLE 3 WATER TREATMENT PLANT CLEARWELL ADDITION PRELIMINARY PROJECT SCHEDULE Time to Cumulative Time Activity Complete To Complete (Days) (Days) 1. Notice to Proceed 0 0 2. Site Visit/Information Gathering/Topographic Survey/Geotechnical 30 30 3. Preliminary Design Memorandum (50% Submittal) 45 75 4. Receive CITY Comments. 14 89 5. Submit 90% Drawings and Specifications 30 119 6. Receive CITY Review Comments 14 133 7. Submit 100% Drawings and Specifications 14 147 8. Receive CITY Review Comments 7 154 9. Submit Final Plans and Specifications along with 7 161 permit applications and final cost opinion 10. Regulatory Permitting Phase 30 191 11. Bidding and Award Phase 60 251 12. Construction Phase (Final) 240 491 13. Project Closeout 30 521 Detailed schedule will be provided upon receipt of authorization to proceed and will include specific submittal dates. (Remainder of page left blank intentionally.) Page 15 of 17 TABLE 4 WATER TREATMENT PLANT CLEARWELL ADDITION LIST OF PROJECT DELIVERABLES DESIGN PHASE A. 50% Design Submittal • Three (3) copies of Preliminary Design Report (memorandum). • Three (3) sets of 11" x 17" Drawings, 50% Complete • Three (3) set of Specifications, 50% Complete 50% Completion Estimate of Probable Construction Cost B. 90% Design Submittal • Three (3) copies of Preliminary Design Report (memorandum). • Three (3) sets of 11" x 17" Drawings, 90% Complete • Three (3) set of Specifications, 90% Complete • 90% Completion Estimate of Probable Construction Cost C. 100% Design Submittal • Three (3) copies of Preliminary Design Report (memorandum). • Three (3) sets of 11" x 17" Drawings, 100% Complete Three (3) set of Specifications, 100% Complete • 100% Completion Estimate of Probable Construction Cost D. Final Design Submittal • Project Final Documents including drawings on 22" x 34" sheets and project specifications on 8-1/2" x 11" sheets for use and distribution by CITY. Twenty (20) sets of project documents, final completion. • Completed permit application and exhibits for signatures by CITY officials (permit fees to be paid by ENGINEER). Signed and sealed drawings for permit submittal shall be provided by ENGINEER. • Specific bid information including a line item unit breakdown for the project for use by the CITY's Purchasing Division for preparation of bid documents. Page 16 of 17 Final estimate of probable construction cost. BIDDING SERVICES (Part of Design Phase) A. Pre -Bid. Addenda, as required to the CITY and/or Contractors. 1!=WOM1 4 Bid Tabulation, 2 copies. Recommendation of Award Letter. The CITY will award contract and issue Notice of Award. Y:\Documents\Tamarac\BD\WTP Clearwell Addition\Task Auth 09-04E.wpd Page 17 of 17 CITY OF TAMARAC WATER TREATMENT PLANT CLEARWELL ADDITION TASK AUTHORIZATION NO. 09-04E TABLE 5 I. DESIGN PHASE DATE'. Apn110, 2009 PERSONNEL a n a 11 ' a TASK DESCRIPTION o u al Of Project Adminisliatlon/Wrap ement 18 18 D2 Date Evaluation and Preliminary Design 16 24 2 D3 Preliminary Design Report 4 16 6 D4 Drawings and Engineering 24 40 472 D5 Specification Preparation 12 40 16 06 Permit Preparation Assistance 2 4 12 4 D7 Final Opinion of Probable ConsWction 4 4 Cost DS Bidding Assistance Services 4 2 4 D9 Bid Evaluation and Recommendation of 2 2 2 Award Assistance 010 Submit and Review(Quality Control) 6 8 D11 Regulatory Agency Permit fees D12 Not Used Total Hours 20 78 0 0 148 0 472 0 0 0 d$4,452.00 521600 $186.00 $0,00 $93.00 $87GO $73.00 $87.00 $000 $7600 $10500 Rate $4,32000 $14,508.00 $0,00 $0.00 $12,876.00 $0.00 $41.064.00 $0.00 $000 $0,00TOTAL Sub -Total Labor DESIGN PHASE LABOR $77,2 lI REIMBURSABLE EXPENSES DESIGN PHASE EXPENSE ITEM EXPENSE TYPE UNIT No. OF UNITS COST PER UNIT TOTAL COST 1 REPRODUCTION SET 20 $43.00 $86000 2 PHOTOCOPIES EA 1,000 1$0.20 $200.00 PLOTTING 3 22 X 34(SET UP) EA 82 $1500 $1,23000 11 X 17 (SET UP) EA 164 $3 00 $492.00 TRAVEL 4 MILEAGE MILE 210 $0,55 $116,60 TOLLS EA 0 $0.00 $0.00 SUBCONSULTANTS SURVEY LS 1 $5500,00 $5,500.00 ELECTRICAL LS 1 $38,60000 $38.500,00 STRUCTURAL LS 1 $8,250.00 $8,250,00 5 GEOTECHNICAL LS 1 $5,005.00 $5,005.00 HYDROGEOLOGIC LS 0 $0.00 $0.00 PERMIT FEES LS 1 $42000 $42000 HVAC LS 1 $1,650.00 $1,650.00 TOTAL DESIGN PHASE EXPENSES $81 802.50 GRAND TOTAL $139,000.00 Y:N0CIIMEN1e\TamaracW43 C1 Deslin scope