HomeMy WebLinkAboutCity of Tamarac Resolution R-2001-060Temp. Reso. #9307
February 22, 2001 1
Revision 2, March 21, 2001
CITY OF TAMARAC, FLORIDA
RESOLUTION NO. R-2001- 40
A RESOLUTION OF THE CITY COMMISSION OF THE CITY
OF TAMARAC, FLORIDA, AUTHORIZING THE
APPROPRIATE CITY OFFICIALS TO AWARD BID NO. 00-
21 B TO, AND EXECUTE A CONTRACT WITH, THE LOWEST
RESPONSIVE AND RESPONSIBLE BIDDER, COOPER
CONTRACTING, INC., FOR AN AMOUNT OF $216,933.00
FOR PUMP STATIONS 12 AND 22 REHABILITATION
PROJECT; AND APPROVING FUNDING FOR THIS
PROJECT FROM THE APPROPRIATE UTILITIES
OPERATIONAL AND CIAC ACCOUNT INCLUDING THE
APPROPRIATION OF $213,768.00 FROM RETAINED
EARNINGS IN THE UTILITIES OPERATIONAL FUND AND
$3,165.00 FROM CIAC FUNDS FOR CONSTRUCTION AND
APPROVING AN ADDITIONAL $23,527 FOR ENGINEERING
FEES RELATED TO THIS PROJECT TO HAZEN & SAWYER
FROM UTILITY FUND RETAINED EARNINGS;
AUTHORIZING THE APPROPRIATE CITY OFFICIALS TO
ADMINISTER THE CONTRACT; PROVIDING FOR
CONFLICTS; PROVIDING FOR SEVERABILITY; AND
PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the city of Tamarac owns, operates and maintains
seventy four (74) wastewater pump stations; and
WHEREAS, wastewater pump stations 12 and 22 were constructed in
the early 1970's; which are located at 4747 Treehouse Lane and 7150 NW
82"d Street respectively. (A copy of which is attached hereto in map form as
1
Temp. Reso. #9307
February 22, 2001 2
Revision 2, March 21, 2001
Exhibit 1); and
WHEREAS, the deteriorated condition of these stations has reduced their
efficiency; and
WHEREAS, in accordance with the utilities department's mandate to improve,
renew and rehabilitate existing water and wastewater systems to ensure a safe, reliable
and adequate water supply and wastewater systems to all residents and customers of
the City, pump stations 12 and 22 Rehabilitation project was recommended, approved
and funded as a Capital Improvement Project; and
WHEREAS, the Utilities Department retained the service of Hazen & Sawyer,
one of the City's Consulting Engineers, to complete the design and provide construction
administration services in accordance with the city consulting engineering agreement as
authorized by the city on July 10, 1996, Resolution Number R-96-163; and
WHEREAS, the City of Tamarac advertised Bid No. 00-21 B for pump stations 12
and 22 Rehabilitation project ; and
1
1
Temp. Reso. #9307
February 22, 2001 3
Revision 2, March 21, 2001
WHEREAS, on January 24, 2001, the following bids were opened:
COMPANY NAME
TOTAL, BID $
Cooper Contracting, Inc.
216,933.00
Akerblom Contracting,
Corp.
283,001.00
Azurix N.A.
283,653.48
Asphalt Consultants, Inc.
291,001.00
Trip Development, Corp.
296,001.00
South Florida Utilities, Inc.
332,051.00
Bee Bros. Development,
Inc.
368,949.00
Acutec, Inc.
375,001.00
Intrastate Construction,
Corp.
378,203.00
WHEREAS, Cooper Contracting, Inc. had the lowest bid proposal of
$216,933.00; and
WHEREAS, approved funds in the amount of $3,165.00 are available in CIAC
Account; and
WHEREAS, it is recommended that additional funds in the amount of
$213,768.00 for construction and $23,527 for engineering fees to Hazen & Sawyer be
1
1
Temp. Reso. #9307
February 22, 2001 4
Revision 2, March 21, 2001
appropriated from Retained Earnings to fully fund this project; and
WHEREAS, it is the recommendation of the Director of Utilities and
Purchasing/Contracts Manager that the project be fully funded and that Bid No. 00-21 B
be awarded to the lowest responsive and responsible bidder, Cooper Contracting , Inc.;
and
WHEREAS, the City Commission of the City of Tamarac, Florida deems it to be
in the best interest of the citizens and residents of the City of Tamarac to approve the
award of Bid No. 00-21 B for pump stations 12 and 22 Rehabilitation Project to Cooper
Contracting, Inc., at a cost of $216,933.00.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF TAMARAC, FLORIDA, THAT:
SECTION 1: The foregoing "WHEREAS" clauses are hereby ratified and
confirmed as being true and correct and are hereby made a specific part of this
resolution.
SECTION 2: Bid No. 00-21 B for pump stations 12 and 22 Rehabilitation
1
u
Temp. Reso. #9307
February 22, 2001 5
Revision 2, March 21, 2001
Project is hereby awarded to and that all appropriate City Officials are authorized to
execute the contract between the City of Tamarac and Cooper Contracting, Inc.
(attached hereto as "Exhibit 2")
SECTION 3: A budget appropriation in the amount of $213,768.00 for
construction from Retained Earnings is hereby approved for correct accounting
purposes combined with the $3,165.00 from CIAC, and the construction contract is fully
funded in the amount of $216,933.00.
SECTION 4: A budget appropriation in the amount of $23,527.00 for
engineering fees relating to this project to Hazen & Sawyer from Retained Earnings in
the utilities funding is hereby approved.
SECTION 5: The City Manager, or his designee, be authorized to make
changes, issue Change Orders not to exceed $10,000 per Section 6-156(b) of the City
Code, and close the contract award including, but not limited to, making final payment
and releasing bonds when the work has been successfully completed within the terms
and conditions of the contract and within the contract price.
SECTION 6: All resolutions or parts of resolutions in conflict herewith are
1
1
Temp. Reso. #9307
February 22, 2001 6
Revision 2, March 21, 2001
hereby repealed to the extent of such conflict.
SECTION 7: If any clause, section, other part or application of this
Resolution is held by any court of competent jurisdiction to be unconstitutional or
invalid, in part or application; it shall not affect the validity of the remaining portions or
applications of this Resolution.
SECTION 8:
passage and adoption.
This Resolution shall become effective immediately upon its
PASSED, ADOPTED AND APPROVED this 28'h day of March, 2001.
/ JOE SCHREIBER
C MAYOR
ATTEST:
MARION S NSON, CMC
CITY CLERK
I-HERE15Y CERTIFY that I have
RG/TR/db
CITY A
" rKAf- I
RNEY
RECORD OF COMMISSION VOTE:
MAYOR SCHREIBER
DIST 1: COMM. PORTNER
DIST 2: COMM. MISHKIN
DIST 3: V/M SULTANOF _
DIST 4: COMM. ROBERTS
EXHIBIT 1
TEMP. RESO. # 93 v7
ram►sm
1PUMP STATION #22
CRMEgNAL
T
0
Z
1u SITE
IDPION PUMPSTATION #12
DA1L EY RD
umr�T[n
�tM ? n VlllAl[ � INtlV/RB L'ON1Y
�se _
7 Y LAWI SEC 12
1
PS12_PS22.DWG
CONSTRUCTION CONTRACT AWARD FOR
PUMP STATIONS 12 & 22 REHABILITATION
AGREEMENT
BETWEEN THE CITY OF TAMARAC
I_1.1 D
COOPER CONTRACTING, INC.
6
THIS AGREEMENT is made and entered into this day of 2001
by and between the City of Tamarac, a municipal corporation with principal offices located
at 7525 N.W. 88th Ave., Tamarac, FL 33321 (the "CITY") and Cooper Contracting, Inc., a
Florida corporation, with principal offices located at 5800 S.W. 177th Avenue, Suite 106,
Miami, Florida 33193 (the "CONTRACTOR") to provide for construction of Pump Stations
12 and 22 Rehabilitation.
Now therefore, in consideration of the mutual covenants hereinafter set forth, the
CITY and CONTRACTOR agree as follows:
1) The Contract Documents
The contract documents consist of this Agreement, conditions of the contract
(General, Supplementary and other Conditions), drawings, specifications, all addenda
issued prior to, and all modifications issued after execution of this Agreement. These
contract documents form the Agreement, and all are as fully a part of the Agreement if
attached to this Agreement or repeated therein.
2) The Work
The CONTRACTOR shall perform all work for the City required by the contract
documents as set forth below:
a) The work of this contract consists of rehabilitation of existing City of Tamarac Pump
Stations 12 and 22. The rehabilitation of the pump stations shall include, but not be
limited to demolition, by-pass pumping, pumps and motors, concrete top slabs and
valve boxes, mechanical piping, electrical and control equipment installation, all as
shown on the drawings and in accordance with the information provided in the Contract
Documents.
b) CONTRACTOR shall clean up and remove each day all debris and material created by
the work at the CONTRACTOR's expense.
1
c) CONTRACTOR shall supervise the work force to ensure that all workmen conduct
themselves and perform their work in a safe and professional manner. CONTRACTOR
shall comply with all OSHA safety rules and regulations in the operation of equipment
and in the performance of the work. CONTRACTOR shall at all times have a competent
field supervisor on the job site to enforce these policies and procedures at the
CONTRACTOR's expense.
d) All equipment must be stored in a safe manner when not in operation. The CITY shall
not be responsible for damage to any equipment or personal injuries caused by the
CONTRACTOR's failure to safely store equipment.
e) CONTRACTOR shall provide the CITY with seventy-two (72) hours written notice prior
to the beginning of work under this Agreement and prior to any schedule change with
the exception of inclement weather.
f) CONTRACTOR shall comply with any and all Federal, State, and local laws and
regulations now in effect, or hereinafter enacted during the term of this Agreement,
which are applicable to the CONTRACTOR, its employees, agents, or subcontractors, if
any, with respect to the work and services described herein.
g) CONTINUING USE OF EXISTING FACILITIES: Pump Stations 12 and 22 are part of a
regional facility that must be kept in service at all times. Should the CONTRACTOR fail
to maintain the continuous operations of a bypass pumping system while performing
rehabilitation work, the Owner will repair/operate the bypass pumping system to
maintain station operations. The CONTRACTOR shall reimburse the Owner for any
and all labor and/or material costs incurred in repairing/operating the system.
3) Insurance
CONTRACTOR shall obtain at Contractor's expense all necessary insurance in such
form and amount as required by the City's Risk Manager before beginning work under this
Agreement including, but not limited to, Workers' Compensation, Commercial General
Liability, and all other insurance as required by the City, including Professional Liability
when appropriate. CONTRACTOR shall maintain such insurance in full force and effect
during the life of this Agreement. CONTRACTOR shall provide to the City's Risk Manager
certificates of all insurances required under this section prior to beginning any work under
this Agreement. The CONTRACTOR will ensure that all subcontractors comply with the
above guidelines and will retain all necessary insurance in force throughout the term of this
agreement.
CONTRACTOR shall indemnify and hold the City harmless for any damages
resulting from failure of the CONTRACTOR to take out and maintain such insurance.
Contractor's Liability Insurance policies shall be endorsed to add the City as an additional
4
insured. CONTRACTOR shall be responsible for payment of all deductibles and self-
insurance retentions on Contractor's Liability Insurance policies.
4) Time of Commencement and Substantial Completion
The work to be performed under this Agreement shall be commenced after
execution of the Agreement and not later than ten (10) days after the date of the receipt of
the official Notice -to -Proceed. The work shall be substantially completed no later than one
hundred twenty (120) days after the date of the Notice -to -Proceed. The work shall be
completed no later than thirty (30) days after the date of substantial completion.
6) Contract Sum
The Contract Sum is $216,933.00 (Two hundred sixteen thousand nine hundred
thirty-three dollars and 00/100), which includes a contingency allowance in the amount
of $20,000.00. Payment shall be computed based on lump sum or applying unit prices
to actual units installed and/or worked. Contingency allowance will only be used for
changes in the scope of work due to unforeseen conditions and upon authorization from
the engineer of record.
6) Payments
A monthly payment/progress payment will be made for work that is completed,
inspected and properly invoiced. The CITY shall pay Contractor's itemized invoice on a
monthly basis for work completed. The City shall pay the CONTRACTOR for work
performed subject to the specifications of the job and subject to any additions and
deductions by subsequent change order provided in the contract documents. No payment
will be made for material stored on site.
7) Waiver of Liens
Prior to payment of the Contract Sum, a final waiver of lien shall be submitted by all
suppliers, subcontractors, and/or Contractors who worked on the project that is the subject
of this Agreement.
8) Warranty
CONTRACTOR shall warrant the Pump Stations 12 and 22 Rehabilitation for a
period of one year from the date of completion and final acceptance of work. In the event
that defect occurs during this time, CONTRACTOR shall perform such steps as required in
Section 01700, Paragraph 1.07 and Section 17000, Paragraph 1.09 of the Project
Specifications to remedy the defects. CONTRACTOR shall be responsible for any
damages caused by defect to affected area.
3
9) Indemnification
The CONTRACTOR shall indemnify and hold harmless the CITY, its elected and
appointed officials, employees, and agents from any and all claims, suits, actions,
damages, liability, and expenses (including attorneys' fees) in connection with loss of life,
bodily or personal injury, or property damage, including loss of use thereof, directly or
indirectly caused by, resulting from, arising out of or occurring in connection with the
operations of the CONTRACTOR or its officers, employees, agents, subcontractors, or
independent contractors, excepting only such loss of life, bodily or personal injury, or
property damage solely attributable to the gross negligence or willful misconduct of the
CITY or its elected or appointed officials and employees. The above provisions shall
survive the termination of this Agreement and shall pertain to any occurrence during the
term of this Agreement, even though the claim may be made after the termination hereof.
Nothing contained herein is intended nor shall be construed to waive CITY's rights
and immunities under the common law or Florida Statutes 768.28, as amended from time
to time.
10) Non -Discrimination
The CONTRACTOR agrees that it shall not discriminate against any of its
employees or applicants for employment because of their race, color, religion, sex, or
national origin, and to abide by all federal and State laws regarding non-discrimination.
The CONTRACTOR further agrees to insert the foregoing provisions in all subcontracts
hereunder except subcontracts for standard commercial supplies or raw materials. Any
violation of such provisions shall constitute a material breach of this Agreement.
11) Independent Contractor
CONTRACTOR is an independent contractor under this Agreement. Personal
services provided by the CONTRACTOR shall be by employees of the CONTRACTOR and
subject to supervision by the CONTRACTOR, and not as officers, employees, or agents of
the CITY. Personnel policies, tax responsibilities, social security and health insurance,
employee benefits, purchasing policies and other similar administrative procedures
applicable to services rendered under this Agreement shall be those of the
CONTRACTOR.
12) Assignment and Subcontracting
CONTRACTOR shall not transfer or assign the performance required by this
Agreement without the prior written consent of the City. This Agreement, or any portion
thereof, shall not be subcontracted without the prior written consent of the city.
4
13) Notice
Whenever either party desires or is required under this Agreement to give notice to
any other party, it must be given by written notice, sent by registered United States mail,
with return receipt requested, addressed to the party for whom it is intended at the
following addresses.
Is] IVA
City Manager
City of Tamarac
7525 N.W. 88th Avenue
Tamarac, Florida 33321
With a copy to the City Attorney at the same address.
CONTRACTOR
Mark A. Cooper
President
Cooper Contracting, Inc.
5800 S.W. 177th Avenue, Suite 106
Miami, Florida 33193
14) Termination
This Agreement may be terminated by City or CONTRACTOR for cause or by the
City for convenience, upon seven (7) days of written notice by the terminating party to the
other party for such termination in which event the CONTRACTOR shall be paid its
compensation for services performed to termination date, including services reasonably
related to termination. In the event that the CONTRACTOR abandons this Agreement or
causes it to be terminated, CONTRACTOR shall indemnify the city against loss pertaining
to this termination.
Default by CONTRACTOR: In addition to all other remedies available to the CITY,
this Agreement shall be subject to cancellation by the CITY should the CONTRACTOR
neglect or fail to perform or observe any of the terms, provisions, conditions, or
requirements herein contained, if such neglect or failure shall continue for a period of
seven (7) days after receipt by CONTRACTOR of written notice of such neglect or failure.
I•i
15) Agreement Subject to Funding
This agreement shall remain in full force and effect only as long as the expenditures
provided for in the Agreement have been appropriated by the City Commission of the City
of Tamarac in the annual budget for each fiscal year of this Agreement, and is subject to
termination based on lack of funding.
16) Venue
This Agreement shall be governed by the laws of the State of Florida as now and
hereafter in force. The venue for actions arising out of this agreement is fixed in Broward
County, Florida.
17) Signatory Authority
The CONTRACTOR shall provide the CITY with copies of requisite documentation
evidencing that the signatory for CONTRACTOR has the authority to enter into this
Agreement.
18) Severability; Waiver of Provisions
Any provision in this Agreement that is prohibited or unenforceable in any
jurisdiction shall, as to such jurisdiction, be ineffective to the extent of such prohibition or
unenforceability without invalidating the remaining provisions hereof or affecting the validity
or enforceability of such provisions in any other jurisdiction. The nonenforcement of any
provision by either party shall not constitute a waiver of that provision nor shall it affect the
enforceability of that provision or of the remainder of this Agreement.
19) Merger; Amendment
This Agreement constitutes the entire Agreement between the CONTRACTOR and
the CITY, and negotiations and oral understandings between the parties are merged
herein. This Agreement can be supplemented and/or amended only by a written document
executed by both the CONTRACTOR and the CITY.
0
IN WITNESS WHEREOF, the parties have made and executed this Agreement on
the respective dates under each signature. CITY OF TAMARAC, through its Mayor and
Cooper Contracting, Inc. (Name of party with whom Agreement is made), signing by and
through its President, (President, Owner, C.E.O., etc.) duly authorized to execute same.
AEST:
Marion Swenson, CIVIC
City Clerk
Date: (
ATTEST:
(Corpor to Secretary)
Type/Print Name of Corporate Secy
(CORPORATE SEAL)
7
CITY OF TAMARAC
"-�a
O6 VSchreiber, May/or
Date: �31a v!
Jeffrey r,/Mill&r, City Manager
Date: 3 3 It l
Appr v: d aV form and leg
Suffi i cv: A /
Mitdhell S. Kraft, CitV Aftorney
COOPER CONTRACTING, INC.
(Signal) resid nt)
Mark A. Cooper
Type/Print Name of President
Date: 'i-i -o t
STATE OF FLORIDA
SS
COUNTY OF
I HEREBY CERTIFY that on this day, before me, an Officer duly authorized in the
Sate aforesaid and in the County aforesaid to take acknowledgments, personally appeared
Mark A. Cooper of Cooper Contracting, Inc., a Florida Corporation, to me kno n to be the
person(s) described in and who executed the foregoing instrument and MO-10"
acknowledged before me that he executed the same.
WITNESS my hand and official seal this 0 day ofH444-e' �, 2001.
Personally known to me or
Produced Identification
Signature of Nota Public — State of
Florida at Large
Print, Type Name of Notary
Public tic,QF ���<o LdU +F?DO VILCMEZ
i�C rnkrtip; Nl
v, PU15L:Cj.,, l (urne:i Ex1, 8/?.7,12002
no, CC 771185
✓A
f 1 Fei:on:afly f5;aa�ri 110ther I.D.
Type of I.D. Produced
( ) DID take an oath, or ( ) DID NOT take an oath.
0