HomeMy WebLinkAboutCity of Tamarac Resolution R-87-033Introduced by: L�/i"1 �.� Temp. Reso. #4446
1 REV. 1/26/87
2 CITY OF TAMARAC
3 RESOLUTION NO. R-g7-33
4
A RESOLUTION ISSUING A DEVELOPMENT ORDER FOR
THE BUDGETEL PROJECT; DEVELOPMENT ORDER NO.
6 213 AND PROVIDING AN EFFECTIVE DATE
7 WHEREAS, pursuant to the instructions of the City Council
8 of the City of Tamarac, Florida, a public meeting has been
9 advertised in accordance with applicable law of the date, time
10 and place of the meeting regarding the review of the application
11 for a development order by the applicant for development
12 approval; and
13 WHEREAS, the City Council has examined and investigated the
14 application, staff and Planning Commission recommendations, and
15 the attached Development Review Status Sheet dated 12/18/86; and
16 WHEREAS, the City Council reviewed the development order
17 and accompanying documents at a public meeting; and
8 WHEREAS, the City Council has determined that the applica-
9 tion is in compliance with all elements of its Comprehensive
20 Plan, or will be in compliance prior to the issuance of a Cer-
21 tificate of Occupancy for any unit on the development that is
22 the subject of the application.
23 NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY
24 OF TAMARAC, FLORIDA:
25 SECTION 1: That the development described on the attached
26 development review status sheet dated 12/18/86 is granted a
27 development order to proceed subject to the following
28 conditions:
29 A. Construction is to be in complete compliance with the
30 plans and specifications submitted by the developer to the City
31 of Tamarac as described in Section II of the Development Review
32 Status Sheet and approved engineering drawings.
33 B. Commencement of construction shall be no longer than
34 one year from the date of approval. If the development does not
35 commence construction within one year, this approval is null and
36
. -1-
Temp. Reso. #4446
1
2
3
4
5
6
7
B
9
10
11
12
13
14
15
16
17
B
19
20
21
22
23
24
25
26
27
26
29
30
31
32
33
34
35
36
void unless an extension has been granted in accordance with
applicable neguiations.
C. the development order is assignable, but an assignment
does not discharge any assignee from strict compliance with the
order unless the City Council consents to modify any of the
original requirements.
D. Additional conditions established in order to issue the
development order are set forth as follows:
1. Sprinkler system and standpipe to comply with NFPA #13
and #14.
2. Developer to install reflectorized pavement markers.
SECTION 2: That the City Council hereby accepts and
approves the following documents a a part of this development
order:
1. Public Safety Ingress/Egress Easement.
2. Water Retention Agreement
ES CTION_ 3: Should any section or provision of this
development order be declared by a court of competent juris-
diction to be invalid, the City Council shall determine if the
other portions of the order remain valid or whether the approval
shall be null and void.
qE T30N 4: This development order as conditioned shall
become effective immediately upon passage.
PASSED, ADOPTED AND APPROVED this2day of , 1987.
ATTEST:
ge'� ;f 4zt"
CAROL E. BARBUTO
CITY CLERK
I HEREBY CERTIFY that I have
approved the form and correct-
ness of this RESOLUTION.
A. BANVWPP EGATE
CITT ATTORNEY
BERNARD HART
MAYOR
MAYOR: HART
DIST. 1: C/W MASSARO
DIST. 2: V/M STELZER ZL
DIST. 3: C/M GOTTESMAN
DIST. 4: C/M STEIN
-2-
lk `1
5811 NORTHWEST 88TH AVENUE 0 TAMARAC, FLORIDA 33a21
TELEPHONE (305) 722.5900
DEVELOPMENT REVIEW STATUS SHEET
MEMO #
DATE12/1 86
213 Orig. Dev. Order
Revised Dev. Order
Project BUDGETEL FINAL PLAT AND FINAL SITE PLAN Master File # 8-86
Location South side Commercial Blvd.- east of NW 38 Terr._
Developer BUDGETEL INNS
Owner BUDGETEL INNS
12 23 2 Z
Zoning B-3 Acres 2.150 ac. Recommended Date for Council Action 1/14/87
Future Land Use Designation Commercial Proposed Use 102 bed motel
DEVELOPMENT ORDER FOR:
Final Site Plan x
I. STAFF APPROVAL DATES:
City Planner
City Engineer
Chief Building Official
Fire Chief
Comments
Final Plat x Revised Site Plan
Final Site Plan Final Plat Revised Site Plan
II. PLANNING COMMISSION RECO;I,IENDATIONS:
APPROVAL or APPROVAL WITH CONDITIONS/Date 12/17/86DENIAL/Date
Final Site Plan dated 12/3/86 Rev
Final Plat dated 3/86 Rev Date stamped 12/9/86
Revised Site Plan dated Rev
Planning Commission finding of compliance with Certified Plan:
III. FINAL ENGINEERING DRAWINGS:
APPROVAL/Date APPROVAL AS RMLINED/Date 12/16/86 DENIAL/Date
Comments
cont'd
Page 2
• DEVELOPMENT REVIEW STATUS SNFFT
IV. LANDSCAPE PLAN:
Staff Action
APPROVAL_ APPROVAL WITH CONDITIONS DENIAL
Date 12/2/86
V. BROWARD COUNTY DEVELOPMENT
If applicable) REVIE14 COM14ITTEE REPORT:
---
Comments 1 6/5/86 -
VI. DEVELOPERS AGREEI•1ENTS/FEES (Where applicable): SUMMARY
A. Water and Sewer Developer Agreement
City Engineer Approval/Date
City Attorney Approval/Date
B. Other Development Agreements (Covenants, Stipulations, etc.)
Water Retention Agreement
Utility Easement
Public Safety Ingress/Egress Easement
C. braina a Retention Fee Amount $ „3,�j7 Z-5Q � !
5% Required/Acres Provided
Deficiency/Acres X $35,000/Acre
D. Drainage Improvement Fee Amount $ 279.50
Project Acreage X $130/Acre
E. Water & Sewer N/A
Contribution Charges Fee Amount
Number of ERCs X $1000
F. ERC Review Fee, if ,more than 10 ERCs Fee Amount $ .` _N/A
G. Local Parks/Recreation Fee Amount $ -
Acres Required �..,_ Provided
$/Acre X Deficiency/Acres $20,403.13 Total
750.00 Prepaid
H. Engineering fees fee Amount 1 $19,653.13 Balance
I. Bonds Bond Amount $ $34,826.50
Date: Approved by City Engineer City Attorney
J. On Site Beautification 1,849.57
(Fees to be paid at time of building
($25,868.00 x .0715 =) Permit issuance)
K. Future Traffic Needs $22,644.00
Tn rooms x $222.00 )
cont'd
Page 3 Memo W
MrVrl nOMCNT Dr%17rW CTATIM '�NFFT
DEVELOPMENT REVIEW REQUIREMENTS:
A. Potable Water Service
Certification of City Engineer or Consulting City Engineer of
Availability of Service:
AVAILABLE WILL BE AVAILABLE NOT AVAILABLE
Date Comments
B. Wastewater Treatment and Disposal Service
Certification of City Engineer or Consulting City Engineer of
Availability of
Service:
AVAILABLE X WILL BE AVAILABLE „.M NOT AVAILABLE w
Date Comments
C. Solid Waste Disposal Service
Determination of Availability of Service:
AVAILABLE X' WILL BE AVAILABLE NOT AVAILABLE
Date Comments
D. Drainage Adequacy
Certification of City Engineer or Consulting City Engineer of
Adequacy of Drainage:
ADEQUATE ._ WILL BE ADEQUATE .. NOT ADEQAATE
Date Comments
E. Regional Transportation Network
Compliance wit Minimum Standards:
COMPLIES WILL COMPLY DOES NOT COMPLY
Date Comments
F. Loral Streets and Roads
Compliance wi h Minimum Standards:
COMPLIES WILL COr•1PLY DOES NOT COMPLY
bate Comments
G. Fire Protection Service
Compliance with Minimum Standards:
COMPLIES WILL COMPLY DOES NOT COMPLY
Date Comments
H. Police Protection Service
Compliance wit Minimum Standards:
COMPLIES WILL COMPLY DOES NOT COMPLY
Date Comments
I. Local Parks (Parks and Recreation Facilities)
Ea-nd Deaication Required/Acres _ Provided
Cash in Lieu of Land .___ Gross Acres Max. X ; SAC - $
J.
Compliance with the Standards of the Broward County School Board: 114
SCHOOL SITES NEEDED FOR ELEMENTARY SCHOOL NOT NEED D
of it to MIDDLE SCHOOL NOT NEEDED
"is 00 is HIGH SCHOOL NOT NEEDED
Letter from School Board Dated
Page 4 ks
i�
($0•
DEVELOPMENT REVIEW STATUS SHEET
VIII. PROCESSING FEES (PAID):
Site Plan Review:
Revised Site Plan:
Plat Review:
Schematic Eng.:
Other:
750.00
750.00
150.00 Limited Parking Waiver
STAFF COMMENTS:
Proposed development is/is not in general conformance with Tamarac's Land
Use Plan Element and recommends:
Adoption of Development Order # 213_ _ Master File # _ a-R6 For:
BUDGETEL FINAL PLAT AND FINAL SITE PLAN
Project subject to the requirements included in the Report and the following
conditions:
Staff recommends approval of the final plat and final site plan,
subject to the following items being added to the final site plan:
Sprinkler system and standpipe to comply with NFPA #13 and 14
Developer to install reflectorized pavement markers.